Results - 801 records found - $198,916 Million.
Export CSV| Project | Sector | Company | Municipality | Constituency | REIR | Cost ($M) | Status | Schedule | Remarks |
|---|---|---|---|---|---|---|---|---|---|
| 'Frontier' Oil Sands Mine Phases 1 and 2 | Oil Sands | Teck Coal Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $14,500.0 | Proposed | Proposed construction start phase 1 in 2016. Application filed November 2011. Approval expected in 2015. Four phases in total. | |
| 'Fort Hills' Oil Sands Mine | Oil Sands | Fort Hills Energy Corp. (Suncor Energy Inc. / Total SA / Teck Cominco) | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $9,600.0 | Proposed | Proposed. Presentation to Suncor for corporate approval in 2013. Plans to come onstream pushed back one year to 2017. | |
| 'Kearl Lake' Oil Sands Project Phase 2 of 2 | Oil Sands | Imperial Oil Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $8,900.0 | Under Construction | 2011-2014 | Under construction. Horton CBI Ltd. |
| Joslyn North Mine | Oil Sands | Total E&P Canada Ltd. / Suncor Energy Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $8,900.0 | Proposed | 2013-2017 | Proposed. ERCB conditional approval January 2011, federal approval December 2011. Presentation for Suncor corporate approval in 2013. FEED underway. |
| Natural Gas to Liquid Fuel Plant (Refinery) | Oil and Gas | Sasol Canada | Strathcona County | Fort Saskatchewan-Vegreville | Capital | $8,000.0 | On Hold | On hold. FEED study delayed. | |
| North West Bitumen Upgrader Phase 1 | Oil Sands | North West Redwater Partnership (Canadian Natural Resources Ltd. (CNRL) / North West Upgrading Inc.) | Redwater | Athabasca-Sturgeon-Redwater | Capital | $5,700.0 | Announced | 2013-2016 | Announced. Planned construction start (site work) spring 2013. EPC SNC-Lavalin, PCL Industrial Management. Site modules and mechanical work 2014 - 2015. |
| Trans Mountain Pipeline Expansion | Pipelines | Kinder Morgan Canada | Strathcona County | Sherwood Park | Capital | $5,400.0 | Proposed | 2016-2017 | Proposed. Facilities application to be filed with National Energy Board in late 2013. Open house Coast Edmonton Plaza Hotel May 16 from 4-8pm |
| 'Voyageur South' Oil Sands Mining Operation | Oil Sands | Suncor Energy Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $4,400.0 | Proposed | Proposed. Application filed July 2007. Corporate approval January 2008. | |
| 'Pike' Oil Sands Project | Oil Sands | Devon NEC Corp. (Devon Canada / BP Canada) | Lac La Biche County | Fort McMurray-Conklin | Northeast | $3,800.0 | Proposed | Proposed for development in three phases by 2020. Application filed June 2012. Regulatory approval expected by end of 2013. | |
| Two New Mine Trains, Mildred Lake Mine Site | Oil Sands | Syncrude Canada Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $3,600.0 | Under Construction | 2012-2014 | Under construction |
| 'Carmon Creek' VSD Bitumen Project | Oil Sands | Shell Canada Ltd. | Peace River | Lesser Slave Lake | Peace Country | $3,450.0 | Proposed | 2014-2018 | Proposed. Two central processing facilities and three co-generation units. Regulatory approval granted. Corporate approval by May 2014 |
| 'Grand Rapids' Dual Pipeline | Pipelines | Grand Rapids Pipeline Limited Partnership | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $3,000.0 | Proposed | Proposed. Diluent pipeline in operation by 2015, larger pipeline completed mid-2017 | |
| 'Sunrise Thermal Project' SAGD Oil Sands Project | Oil Sands | Husky Energy Inc. / BP PLC | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $2,700.0 | Under Construction | 2011-2014 | Under construction. SaipamSpA. Application approved. Corporate approval Nov 2010. WorleyParsons Canada EPC field facilities. |
| Christina Lake Thermal Expansion Project | Oil Sands | Cenovus Energy Inc. | Lac La Biche County | Fort McMurray-Conklin | Northeast | $2,700.0 | Under Construction | 2012-2016 | Under construction (phase E). Application approved April 2011. Estimated construction Phase 1E 2012 - 2014; Phase 1F 2012 - 2015; Phase 1G 2014 - 2016. |
| 'Dover' Commercial Oil Sands Project Phase 1 | Oil Sands | Dover Operating Corp. (Dover OPCO) | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $2,500.0 | Proposed | Proposed. Application filed February 2011. Five phases in total. ERCB public hearing begins April 23. Regulatory approval expected late 2013. | |
| 'Equinox' Oil Sands Mine (Lease 14) | Oil Sands | Teck Coal Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $2,500.0 | Proposed | Proposed. Application filed with Frontier application in November 2011. | |
| 'Stonegate Landing' Retail, Office and Industrial | Commercial / Retail | WAM Development Group / AIMCo | Calgary | Calgary-McCall | Calgary | $2,250.0 | Under Construction | 2010-2021 | Under construction. Stoney Industrial Centre warehouse 4 completed, buildings 5 and 6 under construction. Possible construction start retail component (StoneGate Common) in 2014. StoneGate Corporate Centre (office campus) has been deferred. |
| 'Project Horizon' Mining and Drilling Project | Oil Sands | Canadian Natural Resources Ltd. (CNRL) | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $2,060.0 | Under Construction | 2012-2015 | Under construction. Approved Jan 2004. EPC Technip.EPC froth treatment plant SNC Lavalin. |
| 'Foster Creek' Oil Sands Project Phases F, G and H | Oil Sands | Cenovus Energy Inc. / ConocoPhillips | Bonnyville | Bonnyville-Cold Lake | Northeast | $2,000.0 | Under Construction | 2012-2017 | Under construction. ERCB approval September 2010. |
| 'Nabiye' Oil Sands Project Phases 1 - 3 | Oil Sands | Imperial Oil Ltd. | Cold Lake | Bonnyville-Cold Lake | Northeast | $2,000.0 | Under Construction | 2012-2015 | Under construction. Planned on - stream by 2015. Includes a 170MW cogen plant. Corporate approval February 2012. |
| 'Pelican Lake Grand Rapids' SAGD Oil Sands Project | Oil Sands | Cenovus Energy Inc. | M.D. of Opportunity No. 17 | Lesser Slave Lake | Slave Lake | $2,000.0 | Proposed | 2014-2017 | Proposed. Application filed December 2011. Phase 2 2017 - 2021, phase 3 2020 - 2024. |
| 'Surmont Phase 2' Oil Sands Development | Oil Sands | ConocoPhillips Canada / Total Canada | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $2,000.0 | Under Construction | 2010-2015 | Under construction. Bantrel Inc. |
| Athabasca Oil Sands Project Debottleneck | Oil Sands | Shell Canada Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $2,000.0 | Proposed | Proposed. Muskeg River Mine, Jackpine Mine and Scotford. | |
| Sports and Entertainment Development, Edmonton | Commercial / Retail and Residential | Katz Group / WAM Development Group | Edmonton | Edmonton-Centre | Capital | $2,000.0 | Proposed | Proposed. Pending approval of downtown hockey arena. | |
| Centrifuge Plant for Mature Fine Tailings Process | Oil Sands | Syncrude Canada Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,900.0 | Proposed | 2014-2015 | Proposed. Multi-year project with planned completion first half 2015. Module fabrication KBR Industrial Canada. |
| Anthony Henday Drive NE Divided Roadway | Infrastructure | Alberta Transportation | Edmonton | Edmonton-Manning | Capital | $1,810.0 | Under Construction | 2012-2016 | Under construction. Flatiron - Dragados - Aecon - Lafarge JV. |
| LRT Southeast Downtown to Mill Woods/Lewis Farms | Infrastructure | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $1,800.0 | Proposed | 2015-2019 | Proposed. Cost estimate is for line to Mill Woods and on to Lewis Farms in the west end. Proposed construction timeline is Downtown to Mill Woods |
| Eastern Alberta Transmission Line (500kV) | Power | ATCO Electric Ltd. | Sturgeon County | Athabasca-Sturgeon-Redwater | Capital | $1,650.0 | Announced | 2013-2015 | Announced. Valard Construction. Planned construction start spring 2013. AUC approval November 2012. |
| 'Narrows Lake' In Situ Oil Sands Project | Oil Sands | Cenovus Energy Inc. / ConocoPhillips | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,600.0 | Announced | 2013-2017 | Announced |
| 'Northern Gateway' Bitumen and Condensate Pipeline | Pipelines | Enbridge Pipelines Inc. | Bruderheim | Fort Saskatchewan-Vegreville | Capital | $1,579.0 | Proposed | 2014-2015 | Proposed. Application filed May 2010. Construction cost entire pipeline (Alberta and BC) $5.5 billion. |
| 'Taiga' Oil Sands Project | Oil Sands | Osum Oil Sands Corp. | Cold Lake | Bonnyville-Cold Lake | Northeast | $1,570.0 | Announced | 2013-2018 | Announced. ERCB approval September 2012. Corporate sanction expected in 2013. |
| 'Grouse' In Situ Oil Sands Project | Oil Sands | Canadian Natural Resources Ltd. (CNRL) | Lac La Biche County | Fort McMurray-Conklin | Northeast | $1,530.0 | Proposed | 2015-2017 | Proposed. Application filed February 2012, approval expected second quarter 2014. |
| Western Alberta Transmission Line (500kV) | Power | AltaLink Management Ltd. | Edmonton | Edmonton-Ellerslie | Capital | $1,500.0 | Under Construction | 2013-2015 | Under construction. SNC - Lavelin Group Inc. Application filed March 2011. AUC approval December 2012. |
| International Transborder Concourse | Infrastructure | Calgary Airport Authority | Calgary | Calgary-Mackay-Nose Hill | Calgary | $1,427.0 | Under Construction | 2011-2015 | Under construction. EllisDon Construction. Proposals for baggage handling systems closes April 3. |
| 'Shepard Energy Centre' Power Plant | Power | ENMAX Energy Corp. / Capital Power Corp. | Calgary | Calgary-Fort | Calgary | $1,400.0 | Under Construction | 2011-2015 | Under construction. Kiewit Energy Canada Corp. / Black |
| Christina Lake In Situ Oil Sands Project Phase 2B | Oil Sands | MEG Energy Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,400.0 | Under Construction | 2011-2013 | Under construction. Flint Energy Services Ltd. Corporate approval December 2010. |
| Hangingstone SAGD Commercial Production Project | Oil Sands | Japan Canada Oil Sands Limited (JACOS) / Nexen Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,400.0 | Proposed | 2013-2016 | Proposed. Corporate approval to proceed December 2012. Planned production startup first half of 2016. |
| 'Quest' Carbon Capture and Storage (CCS) Project | Oil Sands | Shell Canada / Chevron / Marathon Oil | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $1,350.0 | Under Construction | 2012-2015 | Under construction. Corporate approval September 2012. EPCM capture facility Fluor. EP pipeline Tri - Ocean Engineering. |
| 'Jackfish' Oil Sands Project Phase 3 | Oil Sands | Devon Canada Corp. | Lac La Biche County | Fort McMurray-Conklin | Northeast | $1,300.0 | Under Construction | 2012-2014 | Under construction. Application approved by ERCB November 2011. |
| 'MacKay River' Oil Sands Project Phase 1 | Oil Sands | Cretaceous Oilsands Holdings Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $1,300.0 | Under Construction | 2012-2014 | Under construction. EP services for Central Plant SNC-Lavelin. |
| 'Kirby South' In - Situ Oil Sands Project Phase 1 | Oil Sands | Canadian Natural Resources Ltd. (CNRL) | Lac La Biche County | Fort McMurray-Conklin | Northeast | $1,250.0 | Under Construction | 2010-2013 | Under construction. Application approved Q3 - 2010. |
| 'Tamarack' Bitumen Project Phase 1 | Oil Sands | Ivanhoe Energy | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,250.0 | Proposed | 2012-2013 | Proposed. Application under review. |
| 'Athabasca' Oil Pipeline Twinning | Pipelines | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,200.0 | Announced | 2013-2015 | Announced. Clearing underway. Planned pipeline construction to start August 2013. ERCB application approved November 2012. |
| Cold Lake Pipeline Twinning Foster Creek | Pipelines | Inter Pipeline Fund | Lac La Biche County | Bonnyville-Cold Lake | Northeast | $1,200.0 | Announced | 2013-2016 | Announced. Aecon Utilities / Robert B Somerville Co. Planned construction start August 2013. |
| Kirby Expansion Phase 1 Oil Sands Project | Oil Sands | Canadian Natural Resources Ltd. (CNRL) | Lac La Biche County | Fort McMurray-Conklin | Northeast | $1,200.0 | Proposed | 2014-2015 | Proposed. Application filed December 2011. Corporate sanction expected Q3-2013. |
| 'McKay' SAGD Project Phases 2A and 2B | Oil Sands | Southern Pacific Resources Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,140.0 | Proposed | 2013-2016 | Proposed for 2013 - 2015 (phase 2A) and 2014 - 2016 (phase 2B). Application filed November 2011. |
| 'Germain' Commercial Demonstration Project Phase 2 | Oil Sands | Laricina Energy Ltd. | Athabasca County | Athabasca-Sturgeon-Redwater | North Central | $1,100.0 | Proposed | 2013-2015 | Proposed. Application for phases 2 to 4 filed November 2011. |
| Cold Lake Pipeline Expansion | Pipelines | Inter Pipeline Fund | Regional Municipality of Wood Buffalo | Bonnyville-Cold Lake | Northeast | $1,100.0 | Under Construction | 2013-2016 | Under construction. Aecon Utilities / Robert B Somerville Co. Proposed to be in service in 2014 (Foster Creek extension/twinning) and 2016 (Narrows Lake). |
| Highway 63 Twinning | Infrastructure | Alberta Transportation | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,100.0 | Announced | 2013-2016 | Announced |
| '225 Sixth' Office Towers | Commercial / Retail | Brookfield Properties Ltd. | Calgary | Calgary-Buffalo | Calgary | $1,000.0 | Proposed | Proposed | |
| 'Access' Pipeline Expansion | Pipelines | MEG Energy Corp. / Devon NEC Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,000.0 | Announced | 2013-2014 | Announced. Banister Pipelines. |
| 'Quarry Park' Mixed-Use Development phases 1 and 2 | Commercial / Retail | Remington Development Corp. | Calgary | Calgary-Acadia | Calgary | $1,000.0 | Under Construction | 2006-2015 | Under construction. Phase 1 completed. Office buildings A and B under construction. |
| 'Telephone Lake ' SAGD Project Phase 1 (Phase A) | Oil Sands | Cenovus Energy Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,000.0 | Proposed | 2014-2018 | Proposed. Owner expects construction start 2014, pending approvals. |
| 'Woodland' Pipeline Extension | Pipelines | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,000.0 | Proposed | 2013-2014 | Proposed. ERCB approval August 2012. Planned construction start summer 2013. |
| Coal Gasification Plant | Oil and Gas | Swan Hills Synfuels | Swan Hills | Barrhead-Morinville-Westlock | Slave Lake | $1,000.0 | On Hold | 2013 | On hold. Project was originally proposed to start construction first half of 2013. Applications filed summer 2012. PCL Industrial Management (syngas processing facility). |
| Polaris Pipeline System Expansion | Pipelines | Inter Pipeline Fund | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $1,000.0 | Proposed | Proposed for in service in mid 2014. Project also includes 100 km of smaller diameter pipeline to provide connections to Foster Creek ad Narrows Lake, and diluent receipt points. | |
| Heartland Pipeline and TC Terminal | Pipelines | TransCanada Corporation | Bruderheim | Fort Saskatchewan-Vegreville | Capital | $900.0 | Proposed | Proposed. Planned to be in service second half of 2015. Terminal application to be files spring 2013, pipeline application fall 2013. | |
| Western Reach Pipeline System | Pipelines | Keyera Corp. / Plains Midstream Canada ULC | Saddle Hills County | Dunvegan-Central Peace-Notley | Peace Country | $900.0 | Proposed | Proposed. Possible completion by end of 2015. | |
| 'Vista' Thermal Coal Mine Phase 1 | Mining | Coalspur Mines Ltd. | Hinton | West Yellowhead | West Yellowhead | $870.0 | Proposed | 2013-2015 | Proposed, pending approvals. Possible corporate approval mid-2013, pending regulatory approval and financing. Project includes 6.5 km railway spur. |
| Downtown Performing Arts Centre | Commercial / Retail | Edmonton Academic and Cultural Foundation | Edmonton | Edmonton-Highlands-Norwood | Capital | $850.0 | Proposed | 2014-2017 | Proposed, pending fundraising. Interest in acquiring existing buildings for part of the project. |
| 'Blackrod' SAGD Oil Sands Project Phase 1 | Oil Sands | BlackPearl Resources Inc. | Lac La Biche County | Athabasca-Sturgeon-Redwater | Northeast | $802.0 | Proposed | 2013-2015 | Proposed. Application filed June 2012. Three phases estimated at $2.8 billion. WorleyParsons (FEED), Projex (engineering) |
| Propane Dehydrogenation Facility | Chemicals and Petrochemicals | Williams Energy | Redwater | Athabasca-Sturgeon-Redwater | Capital | $800.0 | Proposed | Proposed. Corporate approval March 2013. Estimated maximum construction cost $900M. Pending approvals. | |
| Transmission Reinforcement, Hanna Region | Power | ATCO Electric Ltd. | Hanna | Drumheller-Stettler | Palliser | $800.0 | Nearing Completion | 2012-2013 | Nearing completion (stage 1). Proposed stage 2 in service at some future date |
| Southeast Section Calgary Ring Road (Stoney Trail) | Infrastructure | Alberta Transportation | Calgary | Calgary-Fort | Calgary | $769.0 | Under Construction | 2010-2013 | Under construction. Chinook Roads Partnership. |
| Metro Line LRT (Downtown to NAIT) | Infrastructure | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $755.0 | Under Construction | 2011-2013 | Under construction. North Link Partnership (SNC Lavelin and Graham Infrastructure). EPCOR Tower tunnel completed. Track being laid through tunnel. |
| Polyethylene Facility Expansion | Chemicals and Petrochemicals | Nova Chemicals | Lacombe County | Lacombe-Ponoka | Central | $750.0 | Announced | 2013-2015 | Announced. Corporate approval March 2013. Ledcor Projects Inc. Project includes addition of a rail yard with room for 450 cars. |
| 'Saleski' Oil Sands Pilot Project Expansion | Oil Sands | Laricina Energy Ltd. | M.D. of Opportunity No. 17 | Fort McMurray-Conklin | Wood Buffalo | $660.0 | Proposed | Proposed | |
| Grande Prairie Regional Hospital | Institutional | Alberta Infrastructure | Grande Prairie | Grande Prairie-Smoky | Peace Country | $620.0 | Under Construction | 2011-2017 | Under construction. Graham Construction. Includes cancer treatment centre. |
| North - South Parallel Runway | Infrastructure | Calgary Airport Authority | Calgary | Calgary-Mackay-Nose Hill | Calgary | $620.0 | Under Construction | 2011-2014 | Under construction. PCL Parsons Dufferin (JV). |
| 'Blackspring Ridge' Wind Power Farm Phase 1 | Power | Enbridge Inc. / EDF Energies Nouvelles | Picture Butte | Little Bow | South Central | $600.0 | Announced | 2013-2014 | Announced. Planned construction start June 2013. Mortenson Construction. |
| 'Great Divide' SAGD Expansion Phase 1 | Oil Sands | Connacher Oil and Gas Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $600.0 | Proposed | Proposed. ERCB approval Sept 2012. | |
| CO2 Pipeline (Alberta Carbon Trunk Line) | Pipelines | Enhance Energy Inc. | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $600.0 | Announced | 2013-2015 | Announced. Capture facilities at Agrium to be constructed 2013-2014. Pipeline construction in 2014-2015. $600M intial cost, with cost totalling $1.2 billion over ten years. |
| Urban Pipeline Replacement Project | Pipelines | ATCO Pipelines | Calgary | Calgary-North West | Calgary | $600.0 | Proposed | Proposed for Edmonton and Calgary. Pending approvals. Open houses in Calgary May 1 and 2. | |
| 'Lindbergh' Thermal Bitumen Project Phase 1 | Oil Sands | Pengrowth Energy Corp. | Bonnyville M.D. No. 87 | Bonnyville-Cold Lake | Northeast | $590.0 | Proposed | 2013-2015 | Proposed |
| 'Heartland' Transmission Line (500kV) | Power | EPCOR Distribution and Transmission / AltaLink Management Ltd. | Edmonton | Edmonton-Ellerslie | Capital | $582.0 | Under Construction | 2012-2013 | Under construction. Alberta Utilities Commission (AUC) approval November 2011. |
| Foothills Medical Centre Upgrade (McCaig Tower) | Institutional | Alberta Health and Wellness | Calgary | Calgary-Mountain View | Calgary | $550.6 | Under Construction | 2006-2014 | Under construction. EllisDon Construction. Main tower complete. Hospital department renovations underway. |
| 'BlackGold' Oil Sands Project Phase 2 | Oil Sands | Harvest Energy Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $540.0 | Proposed | 2013-2015 | Proposed, pending approvals. |
| Hangingstone Oil Sands Phase 1 | Oil Sands | Athabasca Oil Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $536.0 | Under Construction | 2013-2014 | Under construction. Corporate approval November 2012. ERCB approval February 2013. |
| 'Birchwood' SAGD Oil Sands Project | Oil Sands | Marathon Oil Canada Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $510.0 | Proposed | 2013-2015 | Proposed, pending approvals. |
| Bitumen Liquids Extraction Plant | Oil Sands | Williams Energy | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $500.0 | Proposed | Proposed | |
| Christina Lake SAGD Project Phase 3 | Oil Sands | MEG Energy Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $500.0 | Proposed | Proposed. ERCB approval January 2012. Phase 3A planned for completion in 2016. | |
| Office Building Campus (Ten Buildings) | Commercial / Retail | Shepard Development Corp. | Calgary | Calgary-Hays | Calgary | $500.0 | Announced | 2014-2019 | Announced. Phased development. Construction schedule is for phases 1 and 2 |
| Oxford Airport Business Park | Commercial / Retail | Oxford Properties | Calgary | Calgary-Mackay-Nose Hill | Calgary | $500.0 | Under Construction | 2011-2019 | Under construction (Buildings D and E). Elan Construction (Buildings D and E). Multi - phased project will take six to eight years to complete. |
| Power Generation Plant (300MW) | Power | Swan Hills Synfuels | Swan Hills | Barrhead-Morinville-Westlock | Slave Lake | $500.0 | On Hold | 2015 | On hold. Swan Hills / Whitecourt area |
| 'West Ells' Oil Sands Project Phases 1 and 2 | Oil Sands | Sunshine Oilsands | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $496.0 | Under Construction | 2012-2013 | Under construction |
| Downtown Hockey Arena | Tourism / Recreation | City of Edmonton / The Katz Group of Companies / WAM Development Group | Edmonton | Edmonton-Centre | Capital | $480.0 | Announced | 2014-2016 | Announced. PCL Construction. Project manager (arena portion) ICON Venues Group. Approved by city council January 23/2013 and on May 15/2013. Anticipated construction start spring 2014. |
| 'Hoole' SAGD Oil Sands Project Phase 1 | Oil Sands | Cavalier Energy Ltd. | M.D. of Opportunity No. 17 | Lesser Slave Lake | Slave Lake | $452.0 | Proposed | 2014 | Proposed. Planned construction start August 2014, pending regulatory approvals. |
| 'Walleye' Oil Sands Project (SAGD) | Oil Sands | Devon NEC Corp. (Devon Canada / BP Canada) | Bonnyville M.D. No. 87 | Bonnyville-Cold Lake | Northeast | $450.0 | Proposed | 2013-2015 | Proposed. Application filed. Planned construction start mid - 2013, pending approvals. |
| 'Germain' Commercial Demonstration Project | Oil Sands | Laricina Energy Ltd. | Athabasca County | Athabasca-Sturgeon-Redwater | North Central | $435.0 | Nearing Completion | 2011-2013 | Nearing completion |
| 'Thickwood' SAGD Oil Sands Project | Oil Sands | Grizzly Oil Sands ULC | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $420.0 | Proposed | Proposed. Application filed. | |
| 'Clearwater West' SAGD Production Phase 1 | Oil Sands | Alberta Oilsands Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $415.0 | Proposed | Proposed. Application filed January 2010. | |
| Fractionator Twinning (RFS II) | Oil and Gas | Pembina Pipeline Corp. | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $415.0 | Proposed | Proposed to be in service fourth quarter 2015, pending regulatory approvals. | |
| Phase 2 NGL Expansion | Pipelines | Pembina Pipeline Corp. | Saddle Hills County | Grande Prairie-Wapiti | Peace Country | $415.0 | Proposed | Proposed. Planned in service early to mid 2015, pending approvals. | |
| Transmission Line (240kV), Cassils to Bowmanton | Power | AltaLink Management Ltd. | Brooks | Strathmore-Brooks | Palliser | $407.0 | Under Construction | 2011-2014 | Under construction. Route to go north of Lake Newell. |
| 'Wild Rose' Wind Farm Phase 1 (200 MW) | Power | Naturener Energy Canada | Cypress County | Cypress-Medicine Hat | Palliser | $400.0 | Proposed | 2013-2013 | Proposed. AUC approval October 2010. East Palliser Transmission Line approved March 2012. Planned construction start by end of 2013. |
| 'Wood Buffalo' Crude Oil Pipeline | Pipelines | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $370.0 | Under Construction | 2011-2013 | Under construction |
| Four Stage Transmission Upgrade, Red Deer Region | Power | AltaLink Management Ltd. | Red Deer County | Innisfail-Sylvan Lake | Central | $350.0 | Proposed | 2013-2015 | Proposed to start construction in summer 2013, pending approvals. Stage 1 is substation upgrades in Red Deer area; stage 2 is line rebuild in Red Deer and area; stage 3 is new substations and lines in Ponoka, innisfail and Didsbury areas; and stage 4 is removal of some existing lines from Wetaskiwin to Lacombe and Red Deer to Innisfail. |
| South Foothills Transmission Project (240kV) | Power | AltaLink Management Ltd. | Fort Macleod | Livingstone-Macleod | Southwest | $345.0 | Proposed | Proposed construction start summer 2012, pending approvals. | |
| New Royal Alberta Museum, Downtown | Tourism / Recreation | Province of Alberta | Edmonton | Edmonton-Centre | Capital | $340.5 | Announced | 2012-2016 | Announced. Ledcor Design - Build (Alberta) Inc. |
| Off - Gas Extraction Plant Modifications | Oil Sands | Williams Canada | Redwater | Athabasca-Sturgeon-Redwater | Capital | $330.0 | Under Construction | 2012-2013 | under construction (Redwater facility). |
| Edmonton Terminal Storage Expansion Part 1 | Pipelines | Kinder Morgan Canada | Strathcona County | Fort Saskatchewan-Vegreville | Capital | $308.0 | Under Construction | 2012-2013 | UNder construction |
| 'Evolution' Residential / Retail Complex | Residential | Bosa Development / Embassy Development | Calgary | Calgary-Fort | Calgary | $300.0 | Under Construction | 2012-2014 | Under construction. Construction schedule is for Fuse only. Construction of three towers (Fuse, Pulse, one other) over five to seven years. Proposed construction Pulse 2014-2016 |
| Cheecham Terminal Expansion | Pipelines | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $300.0 | Proposed | 2014-2015 | Proposed. |
| Composite Tailings Plant, Aurora North Mine Site | Oil Sands | Syncrude Canada Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $300.0 | Announced | 2012-2013 | Announced |
| Highrise and Medium Rise Buildings, East Village | Commercial / Retail and Residential | FRAM Building Group / Slokker Canada Corp. / Tricon Capital Group | Calgary | Calgary-Fort | Calgary | $300.0 | Proposed | 2013-2015 | Proposed. First condo tower (First) in 2013 - 2015. |
| Airport Trail Tunnel Under New Runway | Infrastructure | City of Calgary | Calgary | Calgary-Mackay-Nose Hill | Calgary | $294.8 | Under Construction | 2011-2014 | Under construction. PCL Parsons Dufferin JV. Tunnel and extension of Airport Tr from Barlow Tr to 36 St NE. |
| Twelve New Schools across Alberta | Institutional | Alberta Education* / ABC Schools Partnership | Airdrie | Airdrie | Calgary | $288.8 | Under Construction | 2012-2014 | Under construction. Clark Builders (Airdrie(2), Chestermere,Medicine Hat,Red Deer) |
| Crude Oil Pipeline Edmonton to Hardisty | Pipelines | Enbridge Inc. | Strathcona County | Sherwood Park | Capital | $286.0 | Proposed | Proposed | |
| Keystone Hardisty Terminal | Pipelines | TransCanada Corporation | Hardisty | Battle River-Wainwright | Battle River | $275.0 | Proposed | Proposed in service late 2014. | |
| Enbridge Edmonton Terminal (South) Expansion | Pipelines | Enbridge Inc. | Strathcona County | Fort Saskatchewan-Vegreville | Capital | $260.0 | Proposed | 2013-2013 | Proposed, pending regulatory approval. |
| Flow Reversal on Cochlin Pipeline | Pipelines | Kinder Morgan Canada | Special Area No. 3 | Drumheller-Stettler | Palliser | $260.0 | Proposed | Proposed. Company affiliate Kinder Morgan Cochlin LLC applying to US govt for reversal on US portion of Cochlin pipeline from Illinois to Canada / US border at Sask/North Dakota). | |
| 'May River' Commercial Bitumen Project Phase 1 | Oil Sands | Grizzly Oil Sands ULC | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $250.0 | Proposed | Proposed. Application to be filed mid 2013. | |
| Kelly Ramsey Building Redevelopment | Commercial / Retail | John Day Developments | Edmonton | Edmonton-Centre | Capital | $250.0 | Proposed | 2013-2015 | Proposed |
| Phase 2 Peace LVP Expansion | Pipelines | Pembina Pipeline Corp. | Greenview M.D. No. 16 | Grande Prairie-Wapiti | Peace Country | $250.0 | Proposed | Proposed to be in service late 2014, pending approvals. | |
| New Downtown Library, East Village | Institutional | City of Calgary | Calgary | Calgary-Cross | Calgary | $245.0 | Proposed | 2014-2018 | Proposed. Received council approval in February 2013. |
| 'Centre in the Park' Development | Residential | Christenson Developments / Western Asset Management Group (WAM) | Strathcona County | Sherwood Park | Capital | $230.0 | Nearing Completion | 2006-2013 | Nearing completion. Can-Der Construction. |
| 'Resthaven' Plant Capacity Expansion | Oil and Gas | Pembina Pipeline Corp. | Grande Cache | West Yellowhead | Peace Country | $230.0 | Under Construction | 2012-2013 | Under construction |
| Medicine Hat Regional Hospital Redevelopment | Institutional | Alberta Infrastructure | Medicine Hat | Medicine Hat | Palliser | $220.0 | Under Construction | 2012-2015 | Under construction. Stuart Olson Dominion Construction. |
| Rimbey Gas Plant Expansion | Oil and Gas | Keyara Corp. | Ponoka County No. 3 | Rimbey-Rocky Mountain House-Sundre | Central | $210.0 | Under Construction | 2012-2014 | Under construction |
| Interchange Highway 2 / 41 Ave | Infrastructure | City of Edmonton | Edmonton | Edmonton-South West | Capital | $205.0 | Announced | 2013-2015 | Announced. Tender cloes May 30. |
| 'Hangingstone' Connector Pipeline | Pipelines | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $200.0 | Proposed | 2014-2015 | Proposed. Pending approvals. Application to be filed May 2013. |
| 'Rainbow Pipeline II' Butane Pipeline | Pipelines | Plains Midstream Canada (Plains) | Slave Lake | Lesser Slave Lake | Slave Lake | $200.0 | Announced | 2012-2013 | Announced |
| 'Saturn' Natural Gas Liquids Extraction Facility | Oil and Gas | Pembina Pipeline Corp. | Hinton | West Yellowhead | West Yellowhead | $200.0 | Under Construction | 2012-2013 | Under construction |
| NAIT Centre for Applied Technologies | Institutional | Northern Alberta Institute of Technology (NAIT) | Edmonton | Edmonton-Calder | Capital | $200.0 | Proposed | Proposed | |
| Polaris Expansion Christina Lake Extension | Pipelines | Inter Pipeline Fund | Lamont | Fort Saskatchewan-Vegreville | Capital | $200.0 | Announced | 2013-2016 | Announced. Aecon Utilities / Robert B Somerville Co. Planned construction start August 2013. |
| Fort McMurray Airport Upgrade / Expansion | Infrastructure | Fort McMurray Regional Airport Authority | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $198.0 | Under Construction | 2011-2014 | Under construction. Ledcor Construction (terminal). Terminal and expanded parking. |
| 'Eighth Avenue Place' Office Development | Commercial / Retail | Alberta Investment Management Corp (AIMCo) / Ivanhoe Cambridge / Matco Investments Ltd. | Calgary | Calgary-Buffalo | Calgary | $195.0 | Under Construction | 2012-2014 | Under construction. |
| Sundance Power Plant Repairs (560MW) | Power | TransAlta | Parkland County | Stony Plain | Capital | $190.0 | Announced | 2012-2013 | Announced |
| Edson Healthcare Centre | Institutional | Alberta Infrastructure | Edson | West Yellowhead | West Yellowhead | $186.0 | Under Construction | 2012-2015 | Under construction. Stuart Olson Dominion Construction. |
| 'Athabasca' Pipeline Capacity Expansion | Pipelines | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $185.0 | Under Construction | 2012-2013 | Under construction |
| Development of #8 and #12 Mines | Mining | Grande Cache Coal Corporation | Grande Cache | West Yellowhead | Peace Country | $180.0 | Nearing Completion | 2009-2012 | Nearing completion. ERCB approval for #8 mine November 2009, #12 July 2011. |
| Biomass Power Generation, La Crete | Power | Mustus Energy | Mackenzie County | Peace River | Mackenzie | $170.0 | Under Construction | 2012-2014 | Under construction. Lockheed Martin. |
| Dentistry / Pharmacy Building Repurposing | Institutional | University of Alberta | Edmonton | Edmonton-Strathcona | Capital | $170.0 | Proposed | Proposed | |
| North Learning Centre (Downtown Campus) | Institutional | NorQuest College | Edmonton | Edmonton-Centre | Capital | $170.0 | Proposed | Proposed | |
| Federal Building Redevelopment | Infrastructure | Alberta Infrastructure | Edmonton | Edmonton-Centre | Capital | $165.0 | Under Construction | 2008-2013 | Under construction. Clark Builders. |
| Zoo Redevelopment Phase 1 | Tourism / Recreation | Calgary Zoo | Calgary | Calgary-Mountain View | Calgary | $162.0 | Proposed | 2013-2018 | Proposed. |
| 'Bull Creek' Wind Farm (110MW) | Power | BluEarth Renewables | M.D. of Provost No. 52 | Battle River-Wainwright | Battle River | $160.0 | Proposed | 2013-2013 | Proposed. Application filed. Public hearing April 29 - May 3 in Provost, May 7 in Calgary. Planned construction start Q3-2013, pending approvals. |
| High Prairie Health Complex | Institutional | Alberta Infrastructure | High Prairie | Lesser Slave Lake | Slave Lake | $160.0 | Under Construction | 2012-2016 | Under construction. Graham Construction. |
| Picture Butte - Etzikom Coulee Transmission Line | Power | AltaLink Management Ltd. | Picture Butte | Little Bow | South Central | $160.0 | Proposed | 2014-2015 | Proposed. |
| Replacement for Walterdale Bridge | Infrastructure | City of Edmonton | Edmonton | Edmonton-Strathcona | Capital | $155.0 | Announced | 2013-2015 | Announced. Planned construction start May 2013. |
| 'Sage' Oil Sands Extraction Pilot Project | Oil Sands | Birchwood Resources Inc. | Cold Lake | Bonnyville-Cold Lake | Northeast | $150.0 | Proposed | 2014-2014 | Proposed. Application filed June 2012. |
| Fertilizer Plant Expansion | Agriculture and Related | Agrium | Redwater | Athabasca-Sturgeon-Redwater | Capital | $150.0 | Proposed | Proposed. Not happening until 2015 at the earliest. | |
| Northside Recreation Centre, Abrams Land | Tourism / Recreation | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $150.0 | Proposed | Proposed. | |
| Regional Water System | Pipelines | Alberta Central East Water Corp. | Vegreville | Fort Saskatchewan-Vegreville | Northeast | $150.0 | Under Construction | 2012 | Nearing completion (phase 2 of 5 phases). Contract 6 Nu Edge Construction. Phase 3 to be constructed in 2013. |
| Stonefell Terminal | Pipelines | MEG Energy Corp. | Strathcona County | Fort Saskatchewan-Vegreville | Capital | $150.0 | Under Construction | 2011-2013 | Under construction |
| Tankage Expansion | Oil Sands | Enbridge Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $150.0 | Under Construction | 2012-2013 | Under construction |
| Schulich School of Engineering Phase 2 | Institutional | The University of Calgary | Calgary | Calgary-Varsity | Calgary | $142.0 | Proposed | Proposed | |
| Provincial Cancer Strategy Calgary Phase 1 | Institutional | Alberta Infrastructure | Calgary | Calgary-Cross | Calgary | $141.0 | Proposed | Proposed | |
| Deerland Peaking Station (190MW) | Power | MAXIM Power Corp. | Bruderheim | Fort Saskatchewan-Vegreville | Capital | $140.0 | Proposed | 2013-2014 | Proposed. To be built next to existing Deerland substation. |
| Work Camp (Dormitory Complex) | Oil Sands | Horizon North Logistics Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $140.0 | Announced | 2012-2014 | Announced |
| 2013 Facility Restoration and Service Improvements | Infrastructure | Calgary Airport Authority | Calgary | Calgary-Mackay-Nose Hill | Calgary | $135.0 | Announced | 2013-2013 | Announced |
| Biofuels Plant, Clover Bar Landfill | Biofuels | Enerkem Greenfield Alberta Biofuels and partners | Edmonton | Edmonton-Beverly-Clareview | Capital | $132.5 | Nearing Completion | 2010-2013 | Nearing completion |
| 'The River' Condominium Building | Residential | 26th Avenue River Investments Inc. | Calgary | Calgary-Buffalo | Calgary | $130.0 | Under Construction | 2012-2015 | Under construction. Ledcor Construction. |
| Mount Royal Village Redevelopment | Commercial / Retail and Residential | First Capital Realty Inc. | Calgary | Calgary-Buffalo | Calgary | $130.0 | Proposed | Proposed | |
| Northeast Transit Garage | Infrastructure | City of Edmonton | Edmonton | Edmonton-Manning | Capital | $130.0 | Proposed | Proposed. | |
| Strathcona Hospital Phase 1 | Institutional | Alberta Infrastructure | Strathcona County | Sherwood Park | Capital | $130.0 | Under Construction | 2010-2014 | Under construction. EllisDon Construction. CASA House completed. Phase 2 cancelled in 2013 provincial budget. |
| Twinning Hwy 1 Km 73 - 82, Banff National Park | Infrastructure | Parks Canada | I.D. No. 9 Banff | Banff-Cochrane | Calgary | $130.0 | Under Construction | 2009-2014 | Under construction. Dawson Construction. Phase 3B completed. |
| Lethbridge - Chinook Regional Hospital | Institutional | Alberta Infrastructure | Lethbridge | Lethbridge-East | South Central | $127.8 | Under Construction | 2012-2015 | Under construction. Stuart Olson Dominion Construction. Phase 1 from 2012 - 2015. |
| Transportation Terminal Expansion | Oil Sands | Canexus Corp. | Bruderheim | Fort Saskatchewan-Vegreville | Capital | $125.0 | Proposed | Proposed | |
| 'Oldman 2' Wind Farm (46MW) | Power | Alberta Wind Energy Corp. / Mainstream Canada | Pincher Creek | Livingstone-Macleod | Southwest | $120.0 | Announced | 2013-2013 | Announced. Planned construction start March 2013. |
| Infrastructure Upgrades, CFB Cold Lake | Infrastructure | Defence Construction Canada | Cold Lake | Bonnyville-Cold Lake | Northeast | $120.0 | Under Construction | 2006-2015 | Under construction. Planned construction start phase 4 (water mains, storm and sanitary sewer, services to existing buiildings, roadwork, telecommunications) in May. |
| McKimmie Block and Tower Rebuild | Institutional | The University of Calgary | Calgary | Calgary-Varsity | Calgary | $120.0 | Proposed | 2014-2015 | Proposed |
| Sour Gas Gathering Pipeline | Pipelines | Keyara Corp. | Yellowhead County | West Yellowhead | West Yellowhead | $120.0 | Announced | 2013-2014 | Announced. Pending approvals. Planned construciton start September 2013. |
| Three Hilton Hotels and a Conference Centre | Tourism / Recreation | Prestige Capital | Calgary | Calgary-Mackay-Nose Hill | Calgary | $117.0 | Under Construction | 2012-2013 | Under construction (Homewood Suites Hotel). Aman Construction. Part of Calgary Airport Village by Hilton. |
| LRT Extension NW to Rocky Ridge / Tuscany | Infrastructure | City of Calgary | Calgary | Calgary-Cross | Calgary | $115.0 | Under Construction | 2009-2014 | Under construction. LRT overpass over Stoney Tr. Graham Construction Group. Civil works Standard General. Bridge upgrade EllisDon Construction. LRT track, station construction start 2012. |
| Edmonton Terminal Storage Expansion Part 2 | Pipelines | Kinder Morgan Canada | Strathcona County | Sherwood Park | Capital | $112.0 | Announced | 2013-2014 | Announced. Planned construction start spring 2013. |
| King Edward Hotel Redevelopment | Tourism / Recreation | Cantos Music Foundation | Calgary | Calgary-Fort | Calgary | $110.5 | Under Construction | 2013-2015 | Under construction. CANA Construction. Museum, recording studio and music centre. |
| Federal Building Parkade and Centennial Plaza | Infrastructure | Alberta Infrastructure | Edmonton | Edmonton-Centre | Capital | $110.0 | Under Construction | 2009-2013 | Under construction. Clark Builders. |
| Fort Edmonton Park Expansion | Tourism / Recreation | Fort Edmonton Park Management Co. | Edmonton | Edmonton-Whitemud | Capital | $110.0 | Proposed | Proposed to take place over seven to ten years. | |
| Gas Processing Plant Upgrade | Oil and Gas | Keyara Corp. | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $110.0 | Proposed | 2013-2014 | Proposed |
| Shell Place (MacDonald Island Park Expansion) | Tourism / Recreation | Regional Municipality of Wood Buffalo / Macdonald Island Park Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $107.9 | Under Construction | 2012-2014 | Under construction. Clark Builders / Turner Construction. Outdoor performance stadium, shared space and conference centre, and tournament centre. |
| Bitumen Conversion to Heavy Oil Pilot Plant | Oil Sands | MEG Energy Corp. | Lamont County | Fort Saskatchewan-Vegreville | Capital | $103.6 | Proposed | 2013-2014 | Proposed, pending approvals. To be located next to Canexus rail terminal. |
| 'Kinosis' Oil Sands Project Phase 1A | Oil Sands | Nexen Inc. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $100.0 | Proposed | 2012-2014 | Proposed |
| 'Mayfair Village' North (Second) Tower | Residential | ProCura Real Estate Services | Edmonton | Edmonton-Centre | Capital | $100.0 | Announced | 2013-2015 | Announced. Possible construction start June 2013. |
| Biodiesel Plant | Biofuels | Northern Biodiesel Limited Partnership (Archer Daniels Midland Canada / Canadian Bioenergy Corp.) | Lloydminster | Vermilion-Lloydminster | Northeast | $100.0 | Proposed | 2013-2015 | Proposed |
| Capacity Increase on Peace and Northern Pipelines | Pipelines | Pembina Pipeline Corp. | Clear Hills County | Dunvegan-Central Peace-Notley | Peace Country | $100.0 | Under Construction | 2012-2013 | Under construction. Five new pump stations and upgrades to five others. |
| Cold Lake Expansion Mainline Twinning | Pipelines | Inter Pipeline Fund | Bonnyville M.D. No. 87 | Bonnyville-Cold Lake | Northeast | $100.0 | Announced | 2013-2016 | Announced. Aecon Utilities / Robert B Somerville Co. Planned construction start August 2013. |
| East Palliser Transmission Line | Power | AltaLink Management Ltd. | Redcliff | Cypress-Medicine Hat | Palliser | $100.0 | Proposed | Proposed to start in 2012, pending approvals. | |
| Highway 1 (TCH) Twinning Km 49 to 63 | Infrastructure | Parks Canada | I.D. No. 9 Banff | Banff-Cochrane | Calgary | $100.0 | Under Construction | 2008-2013 | Under construction |
| Multi - Purpose Facility, Clareview | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Beverly-Clareview | Capital | $93.0 | Under Construction | 2011-2013 | Under construction. Clark Builders. Renovation / expansion of Clareview Twin Arenas, plus new library and High School Completion centre. |
| Exhibition Park Redevelopment | Tourism / Recreation | Exhibition Park | Lethbridge | Lethbridge-East | South Central | $90.8 | Proposed | 2015-2018 | Proposed. Pending funding and approvals. |
| Simonette Gas Plant Modifications | Oil and Gas | Keyara Corp. | Yellowhead County | West Yellowhead | West Yellowhead | $90.0 | Proposed | Proposed | |
| South Cheecham Rail and Truck Terminal Phase 1 | Infrastructure | Enbridge Inc. / Keyera Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $90.0 | Under Construction | 2012-2013 | Under construction |
| Visual Performing Arts Centre | Institutional | Grant MacEwan University | Edmonton | Edmonton-Centre | Capital | $90.0 | Proposed | 2013-2015 | Proposed. Tender call anticipated November 2013. |
| Recreation Centre / Library, Meadows | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Mill Creek | Capital | $88.8 | Under Construction | 2011-2014 | Under construction. PCL Construction Management. |
| 'The Corners I' Condo Tower, The Quarters | Residential | BCM Homes | Edmonton | Edmonton-Highlands-Norwood | Capital | $80.0 | Proposed | 2012-2015 | Proposed |
| Polaris Expansion Edmonton Extension | Pipelines | Inter Pipeline Fund | Lamont | Fort Saskatchewan-Vegreville | Capital | $80.0 | Announced | 2013-2016 | Announced. Aecon Utilities / Robert B Somerville Co. Planned construction start August 2013. |
| Twinning Highway 43 | Infrastructure | Alberta Transportation / Sturgeon Lake Cree Nation | Greenview M.D. No. 16 | Grande Prairie-Smoky | Peace Country | $78.0 | Under Construction | 2013-2014 | Under construction. Petrowest Construction LP. |
| 'Century Crossing' Commercial Development | Commercial / Retail | Camgill Enterprises | Spruce Grove | Spruce Grove-St. Albert | Capital | $75.0 | Under Construction | 2010-2013 | Under construction. Phased development. |
| 'The Quarry' Commercial Development | Commercial / Retail | Springwood Development | Cochrane | Banff-Cochrane | Calgary | $75.0 | Under Construction | 2012 | Under construction (Sobeys). See also Town of Cochrane Centre Ave Redevelopment under Infrastructure. |
| Hilton Hotel, East Village | Tourism / Recreation | Widewaters Group | Calgary | Calgary-Fort | Calgary | $75.0 | Proposed | Proposed | |
| Polaris Expansion Foster Creek Connection | Pipelines | Inter Pipeline Fund | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $75.0 | Announced | 2013-2016 | Announced. Aecon Utilities / Robert B Somerville Co. Planned construction start August 2013. |
| 'The Bella Concert Hall' Conservatory of Music | Institutional | Mount Royal University | Calgary | Calgary-Elbow | Calgary | $73.0 | Proposed | 2012-2014 | Proposed. |
| 'The Guardian' Condo Towers Phase 1 | Residential | Hon Towers Ltd. | Calgary | Calgary-Buffalo | Calgary | $72.5 | Proposed | 2012-2014 | Proposed |
| Polaris Expansion Narrows Lake Connection | Pipelines | Inter Pipeline Fund | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $72.0 | Announced | 2013-2016 | announced. Aecon Utilities / Robert B Somerville Co. Planned construction start August 2013. |
| Bonnybrook Wastewater Treatment Plant Grit Removal | Infrastructure | City of Calgary | Calgary | Calgary-Fort | Calgary | $71.0 | Under Construction | 2012-2014 | Under construction. Graham Construction. |
| Seton Recreation Centre | Tourism / Recreation | City of Calgary | Calgary | Calgary-Fort | Calgary | $70.0 | Proposed | Proposed. Possible construction start winter 2015. | |
| Storage Tanks | Pipelines | Gibson Energy Inc. | Hardisty | Battle River-Wainwright | Battle River | $70.0 | Announced | 2013-2014 | Announced. Site preparation underway |
| Provincial Cancer Strategy Edmonton Phase 1 | Institutional | Alberta Infrastructure | Edmonton | Edmonton-Riverview | Capital | $67.0 | Announced | 2013-2016 | Announced |
| Highway 201 / Nose Hill Drive Interchange | Infrastructure | Alberta Transportation | Calgary | Calgary-North West | Calgary | $66.8 | Under Construction | 2011-2013 | Under construction. Acciona Infrastructure Canada. |
| 'Lewis' SAGD Oil Sands Project | Oil Sands | Oak Point Energy Ltd. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $65.0 | Proposed | 2013-2014 | Proposed |
| 'Station Pointe Greens' Residential Co - operative | Residential | City of Edmonton | Edmonton | Edmonton-Beverly-Clareview | Capital | $65.0 | Proposed | Proposed | |
| 'Ultima Tower' Luxury Condo Development | Residential | Westrich Pacific Corp. | Edmonton | Edmonton-Centre | Capital | $65.0 | Under Construction | 2012-2015 | Under construction |
| Grey Eagle Casino Expansion | Tourism / Recreation | Sonco Gaming LP / Tsuu T'ina First Nation | Rocky View County | Chestermere-Rocky View | Calgary | $65.0 | Announced | 2012-2014 | Announced. Hotel, entertainment centre, conference and banquet facilities. |
| Northwest Campus | Infrastructure | City of Edmonton / Edmonton Police Service | Edmonton | Edmonton-Glenora | Capital | $65.0 | Proposed | Proposed | |
| Graduate and Upper-Year Residences | Institutional | The University of Calgary | Calgary | Calgary-Varsity | Calgary | $64.0 | Proposed | 2013-2015 | Proposed. Tender closes June 20. Planned construction start July. |
| '6th and 10th' Condominium Building | Residential | Lamb Development Corp. / Fortress Real Capital | Calgary | Calgary-Cross | Calgary | $62.0 | Proposed | Proposed | |
| Mayfield Inn Redevelopment | Tourism / Recreation | SilverBirch Hotels and Resorts | Edmonton | Edmonton-Meadowlark | Capital | $62.0 | Announced | 2013-2014 | Announced. Planned construction start September 2013. |
| 'MARK on Tenth' Condo Tower | Residential | Qualex - Landmark Group | Calgary | Calgary-Buffalo | Calgary | $61.5 | Proposed | 2013-2015 | Proposed |
| Regional Event Centre, Box Springs Business Park | Tourism / Recreation | City of Medicine Hat | Medicine Hat | Medicine Hat | Palliser | $61.4 | Proposed | 2013-2015 | Proposed to start construction in May 2013, pending council approval. MHPM Project Managers. |
| 'Calgary City Centre' Development Phase 1 | Commercial / Retail | Cadillac Fairview Corp. | Calgary | Calgary-Cross | Calgary | $60.0 | Under Construction | 2012-2014 | Under construction. PCL Construction. |
| 'The Seed' Affordable Housing Tower | Residential | Mustard Seed Ministry | Calgary | Calgary-Buffalo | Calgary | $60.0 | Under Construction | 2011-2013 | Under construction. Clark Builders. |
| Lower Townsite Redevelopment | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $60.0 | Announced | 2011-2013 | Announced |
| Rocky Ridge Recreation Centre | Tourism / Recreation | City of Calgary | Calgary | Calgary-North West | Calgary | $60.0 | Proposed | Proposed to start construction in 2014 | |
| Evan Thomas Water and Wastewater Facility | Infrastructure | Alberta Infrastructure | Canmore | Banff-Cochrane | Calgary | $59.6 | Announced | 2012-2014 | Announced. Evan - Thomas Provincial Recreation Area. Epcor Utilities. Cost includes plant operation for ten years. |
| Wastewater Treatment Plant Upgrades Phase 2 | Infrastructure | City of Grande Prairie | Grande Prairie | Grande Prairie-Smoky | Peace Country | $58.0 | Under Construction | 2012-2015 | Under construction. Graham Construction and Engineering. |
| 'Vogue' Condo Apartment Building | Residential | LaCaille Group | Calgary | Calgary-Buffalo | Calgary | $57.5 | Proposed | Proposed | |
| Student Physical Activity and Wellness Centre | Institutional | University of Alberta | Edmonton | Edmonton-Strathcona | Capital | $57.0 | Under Construction | 2012-2014 | Under construction. Clark Builders. |
| Infrastructure Upgrades - 'The Armature' | Commercial / Retail | City of Edmonton | Edmonton | Edmonton-Highlands-Norwood | Capital | $56.0 | Under Construction | 2012-2013 | Under construction (new stormwater line and pipe retrofit to handle sewage) |
| 'University City' Condo Towers | Residential | Metropia / Knightsbridge Homes / RioCan | Calgary | Calgary-Varsity | Calgary | $55.0 | Under Construction | 2012 | Under construction. ITC Construction Group. |
| Mail Processing Plant Re - equip and Re - tool | Commercial / Retail | Canada Post | Calgary | Calgary-Cross | Calgary | $55.0 | Under Construction | 2011-2013 | Under construction. Bird Construction. |
| West Side Aquatic Centre | Tourism / Recreation | City of Lethbridge | Lethbridge | Lethbridge-West | South Central | $54.7 | Proposed | Proposed. Planned completion in late 2017 | |
| Land Force Western Area Headquarters, CFB Edmonton | Other Industrial | Defence Construction Canada | Edmonton | Edmonton-Manning | Capital | $54.0 | Under Construction | 2011-2013 | Under construction. Pentagon Structures Ltd. |
| Two High Schools | Institutional | Alberta Education* | Grande Prairie | Grande Prairie-Wapiti | Peace Country | $54.0 | Under Construction | 2012-2014 | Under construction. Clark Builders. |
| Two New High Schools (Grades 9 to 12) | Institutional | Alberta Education* | Grande Prairie | Grande Prairie-Wapiti | Peace Country | $54.0 | Announced | 2013-2014 | Announced. Clark Builders. Part of the Community Knowledge Campus in Grande Prairie. |
| Wastewater Treatment Plant Expansion | Infrastructure | City of Red Deer | Red Deer | Red Deer-North | Central | $53.8 | Proposed | Proposed. North American Construction. | |
| Mereedith Block Retail Building | Commercial / Retail | Remington Development Corp. | Calgary | Calgary-Mountain View | Calgary | $53.5 | Proposed | Proposed | |
| Metis Tr Extension Phase 3 | Infrastructure | City of Calgary | Calgary | Calgary-McCall | Calgary | $52.0 | Announced | 2012-2012 | Announced |
| Highway 63 Grade, Base and Pave - Fort McMurray | Infrastructure | Alberta Transportation | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $51.6 | Under Construction | 2011-2013 | Under construction. Flatiron Constructors. |
| Glenrose Long Term Care Facility | Institutional | Alberta Infrastructure / Alberta Health and Wellness | Edmonton | Edmonton-Calder | Capital | $51.4 | Proposed | Proposed | |
| Rural Potable Water Supply | Pipelines | County of Newell | Brooks | Strathmore-Brooks | Palliser | $51.0 | Under Construction | 2012-2013 | Under construction. Contract 2 Rosemary, Contract 3 Tilley, Contract 4 Rolling Hills. Prequalification tender for Contract 5 Patricia, Contract 6 Brooks west, Contract 8 Ranier / Scandia closes May 2. |
| Highway 22 Grade, Base and Pave plus Bridge | Infrastructure | Alberta Transportation | Drayton Valley | Drayton Valley-Devon | West Yellowhead | $50.8 | Under Construction | 2011-2014 | Under construction. Flatiron Constructors. |
| 'Cardel Place' Recreation Facility Expansion | Tourism / Recreation | City of Calgary / Nose Creek Sports and Recreation Asoociation | Calgary | Calgary-Northern Hills | Calgary | $50.0 | Proposed | Proposed | |
| Apartment Building | Residential | Fort McMurray Family Crisis Society | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $50.0 | Proposed | 2013-2014 | Proposed. Fundraising underway. |
| Canola Processing Facility | Agriculture and Related | Cargill | Camrose County | Wetaskiwin-Camrose | Battle River | $50.0 | Proposed | 2013-2014 | Proposed. Planned construction start June. |
| Fort McMurray Continuing Care Centre | Institutional | Alberta Infrastructure | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $50.0 | Proposed | 2012-2014 | Proposed |
| Liquified Natural Gas Facility, Jumping Pound Gas | Oil and Gas | Royal Dutch Shell | Cochrane | Chestermere-Rocky View | Calgary | $50.0 | Proposed | 2013-2013 | Proposed. Application filed. |
| Perimeter Pathway System (Calgary Greenway) | Tourism / Recreation | Parks Foundation Calgary | Calgary | Calgary-Buffalo | Calgary | $50.0 | Under Construction | 2010-2014 | Under construction. Phase 1 (Airport Tr to 17 Ave SE) completed. Phase 2 from WID Canal to Fish Creek Park. Phase 3 Airport Tr north and then west along north outskirts. |
| Stonefell Tank Terminal | Pipelines | MEG Energy Corp. | Strathcona County | Fort Saskatchewan-Vegreville | Capital | $50.0 | Proposed | Proposed | |
| Bridge Rehabilitation / Replacement | Infrastructure | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $46.5 | Announced | 2013-2015 | Announced. Groat Rd / Stony Plain Rd Innovative Civil Construction. Groat Rd / 102 Ave 2014 - 2015. |
| Red Deer - Central Alberta Cancer Centre (CACC) | Institutional | Alberta Infrastructure | Red Deer | Red Deer-South | Central | $46.0 | Nearing Completion | 2010-2013 | Nearing completion. Stuart Olson Dominion Construction. |
| 'First and Jasper' Commercial / Retail Building | Commercial / Retail | GE Capital Real Estate | Edmonton | Edmonton-Centre | Capital | $45.0 | Under Construction | 2011-2013 | Under construction. Ledcor Construction. |
| Ethylene Handling Facility Addition | Oil and Gas | Pembina Pipeline Corp. | Legal | Barrhead-Morinville-Westlock | Capital | $45.0 | Proposed | Proposed | |
| Hotel, The Quarters | Tourism / Recreation | Shivam Developments | Edmonton | Edmonton-Highlands-Norwood | Capital | $45.0 | Proposed | 2012-2014 | Proposed |
| LRT Bridge to Replace Cloverdale Pedestrian Bridge | Infrastructure | City of Edmonton | Edmonton | Edmonton-Highlands-Norwood | Capital | $45.0 | Proposed | Proposed. Cost estimate ranges from $45M to $65M. Pending council approval. | |
| St. Patrick's Island Bridge | Infrastructure | Calgary Municipal Land Corp. (CMLC) | Calgary | Calgary-Fort | Calgary | $45.0 | Under Construction | 2012-2014 | Under construction (bridge). Graham Construction (bridge). Island redevelopment planned for 2013 - 2014. |
| 'Alura' Apartment Building | Residential | Cove Properties Ltd. | Calgary | Calgary-Buffalo | Calgary | $44.6 | Under Construction | 2012-2014 | Under construction |
| Hospital Parkade | Infrastructure | Alberta Health Services | Red Deer | Red Deer-South | Central | $44.3 | Proposed | Proposed. RFP closes May 24. | |
| LRT Central Station / Jasper Ave Rehabilitation | Infrastructure | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $44.0 | Under Construction | 2012-2013 | Under construction. PCL Construction Management. |
| Agrium Western Event Centre | Tourism / Recreation | Calgary Exhibition and Stampede | Calgary | Calgary-Buffalo | Calgary | $42.6 | Under Construction | 2012-2014 | Under construction. Ledcor Construction. Part of Stampede Park $400M expansion. |
| Peter Lougheed Centre, Women's Health and Vascular | Institutional | Alberta Infrastructure | Calgary | Calgary-Cross | Calgary | $42.5 | Proposed | Proposed. | |
| 'Signature' Condominium Apartment Building | Residential | Westrich Pacific Corp. | Edmonton | Edmonton-South West | Capital | $42.0 | Under Construction | 2013-2014 | Under construction. |
| 'The Fox' Condo Apartment Buildings (2) | Residential | Langham Developments | Edmonton | Edmonton-Centre | Capital | $42.0 | Under Construction | 2012-2015 | Under construction (building 1). Graham Construction and Engineering. |
| 96 Ave N Extension from Harvest Hills to Deerfoot | Infrastructure | City of Calgary | Calgary | Calgary-Northern Hills | Calgary | $42.0 | Nearing Completion | 2010-2013 | Nearing completion. Aecon Construction. |
| Bioenergy Project (Biogas Power Generation)(5.2MW) | Forestry and Related | Millar Western Forest Products Ltd. | Whitecourt | Whitecourt-Ste. Anne | West Yellowhead | $42.0 | Under Construction | 2012-2013 | Under construction |
| Highway 63 Grade, Base and Pave | Infrastructure | Alberta Transportation | Athabasca County | Athabasca-Sturgeon-Redwater | North Central | $41.7 | Under Construction | 2013-2013 | Under construction. Thompson Bros. Construction Ltd. |
| 'Mosaic Mirage' Townhouse Development | Residential | Brookfield Homes | Calgary | Calgary-Hays | Calgary | $40.0 | Nearing Completion | 2011-2013 | Nearing completion. Part of complex destroyed / damaged by fire September 2012. |
| Biomethanization Project, Slave Lake Pulp | Forestry and Related | West Fraser Mills | M.D. of Lesser Slave River No. 124 | Lesser Slave Lake | Slave Lake | $40.0 | Proposed | 2013 | Proposed to start construction mid - year 2013. |
| Conversion of Four Zellers Stores to Target Stores | Commercial / Retail | Target Corporation | Edmonton | Edmonton-Gold Bar | Capital | $40.0 | Under Construction | 2012-2014 | Completed (Mill WOods, Bonnie Doone, West Edmonton Mall). Chandos Construction (Mill Woods and Bonnie Doone). PCL Builders (West Edmonton Mall). Ledcor Construction (Kingsway Garden Mall). Kingsway Garden Mall to be completed late 2013/early 2014. |
| Conversion of Six Zellers Stores to Target Stores | Commercial / Retail | Target Corporation | Calgary | Calgary-Cross | Calgary | $40.0 | Under Construction | 2012-2013 | Under construction. Chinook Centre, Forest Lawn, Market Mall and Shoppes at Shawnessy completed, West Hills, Sunridge Mall later in 2013. |
| Motorsports Raceway | Tourism / Recreation | Badlands Motorsports Resort | Kneehill County No. 48 | Olds-Didsbury-Three Hills | Central | $40.0 | Proposed | Proposed. Public hearing in June. Estimated cost range between $40M and $55M. | |
| New Infrastructure Services Operations Centre | Infrastructure | City of Lloydminster | Lloydminster | Vermilion-Lloydminster | Northeast | $40.0 | Under Construction | 2012-2014 | Under construction. Ledcor Construction Ltd. |
| Origin Spring Creek Seniors Residence | Residential | Spring Creek Mountain Village | Canmore | Banff-Cochrane | Calgary | $40.0 | Proposed | 2013-2015 | Proposed |
| Shallow - Cut Gas Plant | Oil and Gas | Celtic Exploration Ltd. | Fox Creek | Grande Prairie-Smoky | Peace Country | $40.0 | Proposed | Proposed | |
| Taylor Institute for Teaching and Learning | Institutional | The University of Calgary | Calgary | Calgary-Varsity | Calgary | $40.0 | Proposed | Proposed | |
| Vehicle Maintenance Facility Extension | Other Industrial | Defence Construction Canada | Wainwright M.D. No. 61 | Battle River-Wainwright | Battle River | $39.3 | Under Construction | 2011-2015 | Under construction. Dowland Contracting Ltd. |
| Hinton Training Centre Addition / Alterations | Institutional | Alberta Infrastructure / Alberta Sustainable Resource Development | Hinton | West Yellowhead | West Yellowhead | $39.1 | Proposed | Proposed | |
| Hospital Parkade | Infrastructure | Alberta Infrastructure | Grande Prairie | Grande Prairie-Smoky | Peace Country | $38.9 | Proposed | Proposed | |
| 'The Pearl Tower' Apartment Building | Residential | Regency Developments | Edmonton | Edmonton-Centre | Capital | $38.5 | Under Construction | 2010-2014 | under construction |
| Calder, Capilano and Stanley Milner Libraries | Institutional | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $38.5 | Proposed | Proposed | |
| Saline Creek Sanitary Outfall/Waterline Contract 3 | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $38.2 | Announced | 2013-2013 | Announced. Sprague Rosser Contracting. Planned construction start March. |
| 'The Crossings' Ice Arena plus Curling Rink | Tourism / Recreation | City of Lethbridge | Lethbridge | Lethbridge-West | South Central | $38.0 | Announced | 2013-2015 | Announced. Planned construction start late 2013. |
| Biogas Plant | Biofuels | Renew Bioenergy | Bentley | Rimbey-Rocky Mountain House-Sundre | Central | $38.0 | Proposed | Proposed | |
| New Headquarters Building, Ogden Yard | Commercial / Retail | Canadian Pacific Railway | Calgary | Calgary-Fort | Calgary | $38.0 | Proposed | 2013-2013 | Proposed |
| 'Keynote Urban Village' Residential Tower Two | Residential | Keynote Development Corp. | Calgary | Calgary-Buffalo | Calgary | $37.3 | Under Construction | 2011-2013 | Under construction. CANA Management. |
| Modernization (New Gymnasium) | Institutional | Alberta Infrastructure | Carstairs | Olds-Didsbury-Three Hills | Central | $37.0 | Proposed | 2012-2014 | Proposed. Hugh Sutherland School. |
| '11th Avenue Place' Office Building | Commercial / Retail | PRISM Developments | Calgary | Calgary-Buffalo | Calgary | $36.7 | Under Construction | 2012-2013 | Under construction. Graham Construction. |
| Family Leisure Centre Expansion | Tourism / Recreation | City of Medicine Hat | Medicine Hat | Medicine Hat | Palliser | $36.0 | Proposed | Proposed. MHPM Project Managers Inc. | |
| South Operations Centre, Ft. McMurray | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $36.0 | Announced | 2013-2014 | Announced. Bird Construction Co. Planned construction start June. |
| Highway 63 Grade and Bridge Culverts | Infrastructure | Alberta Transportation | Athabasca County | Athabasca-Sturgeon-Redwater | North Central | $35.6 | Under Construction | 2013-2014 | Under construction. Prairie Roadbuilders Ltd.. |
| 'Varsity Landings' Phase 3 | Residential | Statesman Group of Companies | Calgary | Calgary-Varsity | Calgary | $35.0 | Proposed | Proposed | |
| 'Verde in Clearview Ridge' Townhouse Development | Residential | Avalon Central Alberta | Red Deer | Red Deer-North | Central | $35.0 | Nearing Completion | 2011-2013 | Nearing completion |
| Airport Expansion / Redevelopment Site Works | Infrastructure | Fort McMurray Airport Authority | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $35.0 | Under Construction | 2011-2014 | Under construction. E Construction / Ruel Brothers. |
| Airport, Parkland County | Infrastructure | Parkland Airport Development Corp. | Parkland County | Stony Plain | Capital | $35.0 | Proposed | Proposed. Possible construction 2014 - 2015, pending approvals. Cost is for Phase 1 (runway and basic hangars). | |
| Telus Tower Redevelopment | Commercial / Retail | ATB Financial | Edmonton | Edmonton-Centre | Capital | $35.0 | Announced | 2013-2014 | Announced. Delnor Construction. Planned construction start June. |
| Lloydminster Continuing Care Project | Institutional | Alberta Infrastructure | Lloydminster | Vermilion-Lloydminster | Northeast | $34.2 | Under Construction | 2011-2014 | Under construction. Pentagon Structures. |
| Saline Creek Drive and Bridge Project Phase 1 | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $34.0 | Nearing Completion | 2012-2013 | Nearing completion. Sprague - Rosser Contracting. |
| Stollery Children's Hospital Renovations | Institutional | Alberta Infrastructure | Edmonton | Edmonton-Riverview | Capital | $33.7 | Under Construction | 2011-2015 | Under construction. IMRI completed in 2011, surgical suite construction to start in 2013. |
| 2013 Water Main Renewal Program | Infrastructure | EPCOR Water Services Inc. | Edmonton | Edmonton-Centre | Capital | $33.5 | Proposed | 2013-2013 | Proposed |
| Two Hotels plus Restaurant | Tourism / Recreation | Canalta Real Estate | Medicine Hat | Medicine Hat | Palliser | $33.5 | Proposed | 2013 | Proposed pending approvals. Planned construction start spring 2013. |
| Hwy 63 Grading Algar Tower to Horse Creek | Infrastructure | Alberta Transportation | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $33.0 | Under Construction | 2013-2013 | Under construction. Prairie North Construction. |
| Valley Zoo -- Nature's Wild Backyard Precint | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Riverview | Capital | $33.0 | Proposed | Proposed. RFP for design services closes May 9. | |
| Two New Schools (K to Grade 6), Ft. McMurray | Institutional | Alberta Education* | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $32.8 | Proposed | 2013-2014 | Proposed. Saint Kateri School and Walter and Gladys Hill Public Schools. Centron Group. |
| 'Aperture Residential Park' Student Residences | Institutional | University of Lethbridge | Lethbridge | Lethbridge-West | South Central | $32.0 | Under Construction | 2011-2013 | Under construction. Stuart Olson Dominion. |
| Nose Creek Sanitary Trunk Phase B | Infrastructure | City of Calgary | Calgary | Calgary-Klein | Calgary | $32.0 | On Hold | On hold | |
| Second Ice Surface and Sporting Complex | Tourism / Recreation | Town of Peace River | Peace River | Peace River | Peace Country | $32.0 | Proposed | Proposed. In planning stage. Work to take place in four stages. | |
| Biorefinery | Agriculture and Related | BioRefinex Canada | Lacombe | Lacombe-Ponoka | Central | $31.8 | Proposed | 2013-2014 | Proposed, pending completion of financing. All approvals received. |
| 'Muskwa' Heavy Oil Project Phase 1 | Oil Sands | Sunshine Oilsands | M.D. of Opportunity No. 17 | Lesser Slave Lake | Slave Lake | $31.0 | Proposed | Proposed. Five phases in total. | |
| Inner City Arts Hub (King Edward School) | Commercial / Retail | City of Calgary / Calgary Arts Development | Calgary | Calgary-Elbow | Calgary | $31.0 | Proposed | Proposed to start in 2013, and be completed over several years. | |
| 2013 County of Grande Prairie Paving Projects | Infrastructure | County of Grande Prairie | County of Grande Prairie No. 1 | Grande Prairie-Smoky | Peace Country | $30.9 | Announced | 2013-2013 | Announced |
| 'Artists Quarters' Residence, The Quarters | Residential | Artists Urban Village / Arts Habitat Edmonton | Edmonton | Edmonton-Highlands-Norwood | Capital | $30.0 | Proposed | Proposed. Pending funding. | |
| 'Our Parents Home' Supportive Living Spaces | Institutional | Beit Horim Society | Edmonton | Edmonton-Centre | Capital | $30.0 | Under Construction | 2012-2014 | Under construction. ITC Construction Group. |
| 'StoneCreek Village' Retail/Commercial Development | Commercial / Retail | Melcor Development | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $30.0 | Announced | 2012-2014 | Under construction. Clark Builders. |
| Anzac Wastewater Treatment Plant | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $30.0 | Proposed | Proposed. | |
| Ardrossan Wastewater Line | Infrastructure | Strathcona County | Strathcona County | Strathcona-Sherwood Park | Capital | $30.0 | Announced | 2013-2013 | Announced |
| Biodiesel Plant | Biofuels | The Power Alternative Inc. | Smoky Lake | Athabasca-Sturgeon-Redwater | Northeast | $30.0 | Proposed | Proposed | |
| Biodiesel Plant | Biofuels | The Power Alternative Inc. | High Prairie | Lesser Slave Lake | Slave Lake | $30.0 | Proposed | Proposed | |
| Campbell Road Transit Centre / Park and Ride | Infrastructure | City of St. Albert | St. Albert | Edmonton-Calder | Capital | $30.0 | Proposed | Proposed | |
| Capacity Expansion | Chemicals and Petrochemicals | Methanex | Medicine Hat | Medicine Hat | Palliser | $30.0 | Under Construction | 2012-2013 | Under construction |
| Golf Course Redevelopment | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Highlands-Norwood | Capital | $30.0 | Proposed | 2012-2014 | Proposed |
| Infrastructure Recovery Project | Infrastructure | Town of Slave Lake | Slave Lake | Lesser Slave Lake | Slave Lake | $30.0 | Proposed | Proposed. RFP for consultant services closes May 1. | |
| Macdonald Island Pedestrian Bridge | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $30.0 | Proposed | 2013-2014 | Proposed. Tender closes May 28. |
| Motorsports Raceway Phase 1 | Tourism / Recreation | Rockyview Motorsports Park (RMP) | Rocky View County | Airdrie | Calgary | $30.0 | Proposed | Proposed to be in operation in 2015 | |
| Peace Pipeline Expansion | Pipelines | Pembina Pipeline Corp. | Smoky River M.D. No. 130 | Dunvegan-Central Peace-Notley | Peace Country | $30.0 | Under Construction | 2012-2013 | Under construction. |
| Providence Care Cente | Institutional | Father Lacombe Care Centre Foundation | Calgary | Calgary-Fort | Calgary | $30.0 | Proposed | 2013-2015 | Proposed. Planned construction start May. |
| Rebuild of Electricity Infrastructure | Power | AltaLink Management Ltd. | Drayton Valley | Drayton Valley-Devon | West Yellowhead | $30.0 | Under Construction | 2010-2013 | Under construction |
| Synthetic Crude Commercial Demonstration Plant | Oil and Gas | Steeper Energy | Westlock County | Barrhead-Morinville-Westlock | North Central | $30.0 | Proposed | Proposed | |
| Trestle Creek Golf Resort | Tourism / Recreation | Trestle Creek Golf Resort | Parkland County | Whitecourt-Ste. Anne | Capital | $30.0 | Under Construction | 2010-2014 | Under construction. Construction schedule is for golf course. First nine holes completed in 2012, second nine to be ready 2014. |
| Upgrades to Two Pump Stations | Oil and Gas | Pembina Pipeline Corp. | Brazeau County No. 77 | Drayton Valley-Devon | West Yellowhead | $30.0 | Announced | 2012-2012 | Announced |
| Building 700 Office Building, CFB Edmonton | Other Industrial | Defence Construction Canada | Edmonton | Edmonton-Manning | Capital | $29.9 | Nearing Completion | 2011-2012 | Nearing completion. Pentagon Structures Ltd. |
| New Agrifood Research Centre | Agriculture and Related | Alberta Infrastructure | Brooks | Strathmore-Brooks | Palliser | $29.2 | Proposed | Proposed | |
| 'Marriott Renaissance' Hotel, Edmonton Airport | Tourism / Recreation | Platinum Investments | Leduc County | Leduc-Beaumont | Capital | $29.0 | Under Construction | 2011-2013 | Under construction |
| Community Health Centre, Parsons Creek | Institutional | Alberta Infrastructure | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $28.2 | Proposed | Proposed | |
| 'Champagne at Quarry Park' Condo Building 1 | Residential | Remington Development Corp. | Calgary | Calgary-Acadia | Calgary | $28.1 | Under Construction | 2012-2013 | Under construction |
| 'Varsity Landings' Phase 2 | Residential | Statesman Group of Companies | Calgary | Calgary-Varsity | Calgary | $28.0 | Proposed | 2013-2014 | Proposed. Planned construction start June. |
| St. Joseph's College Womens Residence | Institutional | University of Alberta | Edmonton | Edmonton-Riverview | Capital | $28.0 | Proposed | 2013-2015 | Proposed. Call for proposals closes May 16. |
| 'Calla' Apartment Building | Residential | Qualex - Landmark Group | Calgary | Calgary-Buffalo | Calgary | $27.7 | Under Construction | 2011-2013 | Under construction. ITC Construction Group. |
| Auburn Bay Seniors' Residence | Institutional | All Seniors Care Living Centres | Calgary | Calgary-South East | Calgary | $27.7 | Announced | 2012-2013 | Announced |
| 'Glenmore Garden Towers III' Apartment Building | Residential | Realstar Management | Calgary | Calgary-Glenmore | Calgary | $27.5 | Proposed | Proposed. ITC Construction Group. | |
| 'Hangingstone' Oil Sands Phase 1 Infrastructure | Oil Sands | Athabasca Oil Corp. | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $27.0 | Under Construction | 2013-2014 | Under construction |
| Student Residence Buildings A and B in East Campus | Institutional | University of Alberta | Edmonton | Edmonton-Riverview | Capital | $27.0 | Proposed | Proposed | |
| Lethbridge Regional Police HQ Expansion | Infrastructure | City of Lethbridge | Lethbridge | Little Bow | South Central | $26.4 | Announced | 2013-2015 | Announced. Dawson Wallace Construction. |
| 'St. Johns 10th Street' Condominiums | Residential | Streetside Development Corp. | Calgary | Calgary-Mountain View | Calgary | $26.0 | Nearing Completion | 2011-2013 | Nearing completion |
| Water Line Twinning | Pipelines | Mountain View Regional Water Services Commission | Innisfail | Innisfail-Sylvan Lake | Central | $26.0 | Under Construction | 2010 | Under construction (Phase 1 completed). |
| Aquatic and Wellness Centre, Emerald HIlls | Tourism / Recreation | Strathcona County | Strathcona County | Sherwood Park | Capital | $25.8 | Proposed | Proposed | |
| 'Amica at Aspen Woods' Retirement Residence | Institutional | Penner Development Group | Calgary | Calgary-Bow | Calgary | $25.0 | Under Construction | 2012-2013 | Under construction |
| 'Stonecreek Landing' Condo Apartment Complex | Residential | Carlisle Group | Cochrane | Banff-Cochrane | Calgary | $25.0 | Announced | 2012-2014 | Announced |
| Bowden Institute Expansion | Institutional | Public Works and Government Services Canada | Bowden | Innisfail-Sylvan Lake | Central | $25.0 | Under Construction | 2011-2013 | Under construction. Medium security unit Lear Construction Management. |
| Building and Grounds Upgrades, Telus Tower | Commercial / Retail | Telus | Edmonton | Edmonton-Centre | Capital | $25.0 | Under Construction | 2012-2013 | Under construction. |
| Three Apartment Buildings, Timberlands | Residential | Laebon Developments Ltd. | Red Deer | Red Deer-North | Central | $25.0 | Under Construction | 2011 | Under construction. First building completed, second building under construction. |
| Two Hotels | Tourism / Recreation | Zainul and Shazma Holdings Ltd. | Red Deer | Red Deer-North | Central | $25.0 | Proposed | 2013-2014 | Proposed, pending approvals. |
| Philip J. Currie Dinosaur Museum | Tourism / Recreation | Pipestone Creek Dinosaur Bed Project Committee | Wembley | Grande Prairie-Wapiti | Peace Country | $24.8 | Announced | 2013-2014 | Announced. PCL Construction. Construction start spring 2013. |
| Occupational Work Centres | Infrastructure | City of Calgary | Calgary | Calgary-McCall | Calgary | $24.6 | Announced | 2013-2013 | Announced |
| New Headquarters Building CANA Group | Commercial / Retail | CANA Group of Companies | Calgary | Calgary-Acadia | Calgary | $24.2 | Under Construction | 2012-2013 | Under construction. CANA Construction. |
| 2011 Infrastructure Rehabilitation Abasand Heights | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $24.0 | Under Construction | 2011-2013 | Under construction. Sprague Rosser Contracting. |
| 2012 - 2014 Watermain Replacement Program | Infrastructure | City of Calgary | Calgary | Calgary-Buffalo | Calgary | $24.0 | Announced | 2012-2014 | Announced |
| Terwilligar - Centennial Valley Lands Footbridge | Tourism / Recreation | City of Edmonton / River Valley Alliance | Edmonton | Edmonton-Whitemud | Capital | $24.0 | Proposed | Proposed for completion by 2016. | |
| 'Strategic on 4th' Office Building | Commercial / Retail | Strategic Group | Calgary | Calgary-Buffalo | Calgary | $23.9 | Under Construction | 2012-2013 | Under construction |
| Valley Zoo Entrance and Wander Path Project | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Riverview | Capital | $23.5 | Under Construction | 2012-2013 | Under construction. Stuart Olson Dominion Construction. |
| New School (K to Grade 9) | Institutional | Lloydminster Public School Division | Lloydminster | Vermilion-Lloydminster | Northeast | $23.4 | Under Construction | 2012-2014 | Under construction. Marshall - Lee Construction. College Park School. |
| Highway 63 Southbound Bridge Replacement | Infrastructure | Alberta Transportation | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $23.3 | Under Construction | 2011-2014 | Under construction. Innovative Civil Constructors. |
| Bethel Transit Terminal and Park and Ride | Infrastructure | Strathcona County | Strathcona County | Sherwood Park | Capital | $23.0 | Under Construction | 2013-2013 | Under construction. Aman Construction. Project includes relocation of recycle centre. |
| East Calgary Landfill Collection Services Depot | Infrastructure | City of Calgary | Calgary | Calgary-Greenway | Calgary | $23.0 | Announced | 2012-2013 | Announced |
| 'Groves of Varsity' Apartment Building | Residential | Statesman Group of Companies | Calgary | Calgary-Varsity | Calgary | $22.8 | Under Construction | 2012-2013 | Under construction |
| Airplane Hangar | Commercial / Retail | Sunwest Aviation | Calgary | Calgary-Mackay-Nose Hill | Calgary | $22.4 | Nearing Completion | 2012-2013 | Nearing completion. Cana Management. |
| Water Pipeline | Pipelines | Capital Region Northwest Water Services Commission | Edmonton | Edmonton-Manning | Capital | $22.2 | Proposed | Proposed | |
| 'Broadmoor Heritage Plaza' Retail Development | Commercial / Retail | Core Developments / Prism Developments | Strathcona County | Sherwood Park | Capital | $22.0 | Under Construction | 2012-2013 | Under construction |
| Boyle Renaissance Project Ph 2: Renaissance Tower | Residential | City of Edmonton / Metis Capital Housing Corp. / Canadian Paraplegic Assn / Boyle Street Community League | Edmonton | Edmonton-Highlands-Norwood | Capital | $22.0 | Under Construction | 2012-2013 | Under construction. Clark Builders. |
| Funicular (Gondola System) | Tourism / Recreation | City of Edmonton / River Valley Alliance | Edmonton | Edmonton-Centre | Capital | $22.0 | On Hold | Projtect put on indefinite hold. Originally proposed for completion in 2016. | |
| Power Engineering / Process Operator Power Lab | Institutional | Keyano College | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $22.0 | Under Construction | 2012-2013 | Under construction. PCL Constructors Ltd. |
| Water Treatment Plant, Drayton Valley | Infrastructure | Town of Drayton Valley | Drayton Valley | Drayton Valley-Devon | West Yellowhead | $21.1 | Announced | 2013-2015 | Announced. Nason Contracting Group. Planned construction start April. |
| Fort Calgary Expansion and Restoration | Tourism / Recreation | City of Calgary | Calgary | Calgary-Fort | Calgary | $21.0 | Proposed | Proposed. Pending funding. Interpretive centre expansion (possibly 2013-2015), Deane House restoration and Hunt House conservation. | |
| Nose Creek Trunk Upgrade Phase 2 | Infrastructure | City of Calgary | Calgary | Calgary-Mackay-Nose Hill | Calgary | $21.0 | Announced | 2012-2014 | Announced |
| Stoney Industrial Centre Warehouse 6 | Commercial / Retail | WAM Development Group | Calgary | Calgary-Mackay-Nose Hill | Calgary | $20.6 | Under Construction | 2012-2013 | Under construction |
| 'Redstone' Townhouse Development | Residential | Streetside Development Corp. | Calgary | Calgary-McCall | Calgary | $20.0 | Proposed | Proposed | |
| Canola Processing Facility Expansion | Agriculture and Related | Richardson Oilseed Ltd. | Lethbridge | Lethbridge-East | South Central | $20.0 | Proposed | 2014-2015 | Proposed |
| Gilchrist Seniors' Housing Facility Redevelopment | Institutional | Silvera for Seniors | Calgary | Calgary-Cross | Calgary | $20.0 | Proposed | Proposed | |
| Glencoe Club Renovation | Tourism / Recreation | The Glencoe Club | Calgary | Calgary-Elbow | Calgary | $20.0 | Proposed | 2014 | Proposed |
| North Scenic Drive Extension | Infrastructure | City of Lethbridge | Lethbridge | Lethbridge-West | South Central | $20.0 | Under Construction | 2012-2013 | Under construction. Sanitary and storm sewer Richardson Bros (Olds) Ltd. Contract 2 (surface construction) Degraaf Excavating Ltd. |
| Retirement Residence, Lewis Estates | Residential | All Seniors Care Living Centres | Edmonton | Edmonton-South West | Capital | $20.0 | Under Construction | 2011-2012 | Under construction. |
| Wetaskiwin Regional Aquatics Centre | Tourism / Recreation | City of Wetaskiwin / County of Wetaskiwin | Wetaskiwin | Wetaskiwin-Camrose | Central | $19.8 | Under Construction | 2012-2013 | Under construction. PCL Construction. |
| Edmonton Maximum Security Institution Expansion | Institutional | Public Works and Government Services Canada | Edmonton | Edmonton-Manning | Capital | $19.7 | Under Construction | 2011-2014 | Under construction. Maple Reinders. |
| Mill Woods Library, Seniors Centre, Multicultural | Institutional | City of Edmonton | Edmonton | Edmonton-Mill Woods | Capital | $19.3 | Under Construction | 2013-2014 | Under construction. EllisDon Corporation. |
| Algal Carbon Conversion Pilot Project | Oil Sands | CNRL / NRC / Pond Biofuels | Bonnyville M.D. No. 87 | Bonnyville-Cold Lake | Northeast | $19.0 | Proposed | Proposed | |
| Amelia Substation Upgrade | Power | AltaLink Management Ltd. | Bruderheim | Fort Saskatchewan-Vegreville | Capital | $19.0 | Proposed | 2013-2013 | Proposed. |
| Seniors Lodge (Replacement for Turner Lodge) | Institutional | Heartland Housing Foundation | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $19.0 | Announced | 2013-2014 | Announced. Graham Construction and Engineering. To be located on a portion of the 'old' hospital site. |
| Highway 1 Bridge over South Sask | Infrastructure | Alberta Transportation | Medicine Hat | Medicine Hat | Palliser | $18.7 | Under Construction | 2011-2013 | Under construction. Horseshoe Hill Construction. |
| Highway 1 / Dunmore Rd Interchange | Infrastructure | Alberta Transportation | Medicine Hat | Cypress-Medicine Hat | Palliser | $18.5 | Announced | 2013-2014 | Announced. South Rock Ltd. |
| Storm Sewer | Infrastructure | City of Medicine Hat | Medicine Hat | Medicine Hat | Palliser | $18.5 | Under Construction | 2012-2013 | Under construction. South Rock Ltd. |
| The Bridges Phase 2 Site 15 Affordable Housing | Residential | City of Calgary | Calgary | Calgary-Mountain View | Calgary | $18.5 | Under Construction | 2011-2013 | Under construction |
| New Wal - Mart Store, East Hills | Commercial / Retail | Wal - Mart Canada Corp. | Calgary | Calgary-Greenway | Calgary | $18.3 | Proposed | 2013-2013 | Proposed. |
| HDP Phase 2 Building 'A' Warehouse | Commercial / Retail | Hopewell Development | Calgary | Calgary-Mackay-Nose Hill | Calgary | $18.2 | Proposed | Proposed | |
| 50 Ave (Main St) Makeover | Infrastructure | City of Wetaskiwin | Wetaskiwin | Wetaskiwin-Camrose | Central | $18.0 | Under Construction | 2012-2013 | Under construction. Phase 1 (48 St to 50 St) completed. Phase 2 (50 St to 53 St) in 2013. The remainder of downtown (47 St to 48 St and 53 St to 56 St) to be completed at a later date. Phase 1 Carmacks Enterprise. Phase 2 Carmacks Enterprise. |
| Camrose Performing Arts Centre (CPAC) | Institutional | University of Alberta / City of Camrose / Camrose County | Camrose | Wetaskiwin-Camrose | Battle River | $18.0 | Under Construction | 2012-2013 | Under construction. Clark Builders. Fundraising underway. |
| Continuing Care Facility | Institutional | Bethany Care Society | Didsbury | Olds-Didsbury-Three Hills | Central | $18.0 | Under Construction | 2012-2014 | Under construction. Stuart Olson Dominion Construction. |
| Genesis Place Phase 3 | Tourism / Recreation | City of Airdrie | Airdrie | Airdrie | Calgary | $18.0 | Nearing Completion | 2012-2013 | Nearing completion. Bird Construction. |
| Hwy 63 Grading N of Mariana Lake | Infrastructure | Alberta Transportation | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $18.0 | Under Construction | 2013-2013 | Under construction. Thompson Bros (Construction) LP |
| Module Assembly Yard, Sturgeon Industrial Park | Oil Sands | Horton CBI | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $18.0 | Announced | 2012-2012 | Announced |
| Portion of Regional Sanitary Trunk Line | Infrastructure | City of Red Deer | Red Deer | Red Deer-North | Central | $18.0 | Proposed | 2012-2012 | Proposed for fall. |
| Peigan Tr Site Preparation 52 St to East Freeway | Infrastructure | City of Calgary | Calgary | Calgary-Fort | Calgary | $17.9 | Nearing Completion | 2012-2013 | Nearing completion. Standard General. |
| Andrew Davidson Building Renovation 2013 | Infrastructure | City of Calgary | Calgary | Calgary-Buffalo | Calgary | $17.8 | Announced | 2013-2013 | Announced |
| Supply / Install Entrance Signs | Infrastructure | City of Leduc | Leduc | Leduc-Beaumont | Capital | $17.7 | Proposed | Proposed | |
| 108 Street Capital Boulevard Streetscape | Infrastructure | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $17.6 | Under Construction | 2011-2013 | Under construction. Standard General Inc. |
| Firefighter Training Centre / Fire Station 6 | Infrastructure | Strathcona County | Strathcona County | Sherwood Park | Capital | $17.5 | Under Construction | 2011-2013 | Under construction. Krawford Construction. |
| Strathmore Continuing Care | Institutional | Alberta Seniors and Community Supports | Strathmore | Strathmore-Brooks | Calgary | $17.5 | Proposed | Proposed | |
| 'Villa Marie' Designated Assisted Living Facility | Institutional | Covenant Health | Red Deer | Red Deer-North | Central | $17.4 | Under Construction | 2012-2013 | Under construction. Clark Builders. |
| High School (Grades 7 to 12) | Institutional | Alberta Education* | Jasper | West Yellowhead | West Yellowhead | $17.4 | Under Construction | 2012-2014 | Under construction. Clark Builders. |
| 'Evanston Grand Village' Special Care Facility | Institutional | Golden Life Management Corp. | Calgary | Calgary-Mackay-Nose Hill | Calgary | $17.0 | Proposed | Proposed | |
| Evanston Continuing Care Facility | Institutional | Alberta Health and Wellness / Covenant Health | Calgary | Calgary-Mackay-Nose Hill | Calgary | $17.0 | Under Construction | 2012-2014 | Under construction |
| Main Street Revitalization Project | Infrastructure | City of Wetaskiwin | Wetaskiwin | Wetaskiwin-Camrose | Central | $17.0 | Proposed | Proposed. Four phase project. Phase 1 completed in 2012. | |
| Petroleum Centre | Institutional | Lakeland College | Lloydminster | Vermilion-Lloydminster | Northeast | $17.0 | Announced | 2013-2014 | Announced. Fillmore Construction. Planned construction start May 2013. |
| Police Station Renovation / Expansion | Infrastructure | City of Medicine Hat | Medicine Hat | Medicine Hat | Palliser | $16.8 | Under Construction | 2012-2013 | Under construction. Dawson Wallace Construction. |
| Royal Oak Village Seniors Housing | Institutional | Christenson Communities Ltd. / Good Samaritan Society) | Lacombe | Lacombe-Ponoka | Central | $16.8 | Completed | 2011 | Completed (assisted living). Life lease portion in planning stages, planned to start construction late 2013. |
| Groves of Varsity Apartment Building 3 | Residential | Statesman Group of Companies | Calgary | Calgary-Varsity | Calgary | $16.6 | Proposed | proposed | |
| Multiplex Redevelopment, Sylvan Lake | Tourism / Recreation | Town of Sylvan Lake | Sylvan Lake | Innisfail-Sylvan Lake | Central | $16.5 | Proposed | Proposed | |
| Waters Edge Condominiums and Marina | Commercial / Retail and Residential | Sylvan Lake Harbour Ltd. | Sylvan Lake | Innisfail-Sylvan Lake | Central | $16.5 | Under Construction | 2012-2014 | Nearing completion (marina). Condo design nearing completion. Timeline for condo construction dependent on pre-sales. |
| 'Eighty 5 Nine' Mixed Use Building | Residential | Vertical Properties | Calgary | Calgary-Bow | Calgary | $16.3 | Proposed | Proposed | |
| Clarifiers 5 and 7 / UV2 Project | Infrastructure | Alberta Capital Region Wastewater Commission | Strathcona County | Sherwood Park | Capital | $16.3 | Under Construction | 2012-2014 | Under construction. SureForm Construction. |
| East Calgary Landfill Scalehouse and Entrance | Infrastructure | City of Calgary | Calgary | Calgary-Greenway | Calgary | $16.3 | Nearing Completion | 2012-2013 | Nearing completion. Volker Stein Contracting. |
| 'Royal View East' Condo Apartment Building | Residential | Bentall Kennedy Canada LP | Calgary | Calgary-Klein | Calgary | $16.0 | Proposed | Proposed. In preliminary design. | |
| 'STEPS Bridgeland' Condo Apt Building | Residential | Assured Developments | Calgary | Calgary-Klein | Calgary | $16.0 | Proposed | Proposed. Possible construction start fall 2013. | |
| 'Wing Kei' Supportive Living Facility | Institutional | Chinese Christian Wing Kei Nursing Home Association | Calgary | Calgary-Klein | Calgary | $16.0 | Announced | 2012-2013 | Announced. Bird Construction. |
| 2012 - 2014 Sanitary Sewer Replacement / Lining | Infrastructure | City of Calgary | Calgary | Calgary-Cross | Calgary | $16.0 | Announced | 2012-2014 | Announced |
| Agriculture Equipment Dealership | Commercial / Retail | Cervus Agricultural Equipment | Rocky View County | Chestermere-Rocky View | Calgary | $16.0 | Under Construction | 2012-2013 | Under construction. XPS Contracting. |
| Staybridge Hotel | Tourism / Recreation | Penalta Group Ltd. | Edmonton | Edmonton-Meadowlark | Capital | $16.0 | Proposed | 2013-2014 | Proposed. Planned construction start May 2013. |
| Warehouse 3 Metis Tr / Dwight McLellan Tr | Commercial / Retail | Morguard Investments Ltd. / Verus Partners Canada | Calgary | Calgary-McCall | Calgary | $16.0 | Proposed | Proposed. Construction to follow completion and leasing of building 2. | |
| Ray Gibbon Drive Phase 3 | Infrastructure | City of St. Albert | St. Albert | Spruce Grove-St. Albert | Capital | $15.9 | Nearing Completion | 2012-2013 | Nearing completion. Standard General Inc. |
| Sarcee Operations Workplace Centre | Infrastructure | City of Calgary | Calgary | Calgary-West | Calgary | $15.8 | Proposed | Proposed. Tender for phase 1 closes April 19. | |
| Water / Wastewater Service to Bragg Creek | Infrastructure | Rocky View County | Rocky View County | Banff-Cochrane | Calgary | $15.8 | Proposed | Proposed. Citizen's committee has presented a plan to County council. | |
| Road Improvements 17 St from 105 Ave to Sh. Park | Infrastructure | Strathcona County | Edmonton | Sherwood Park | Capital | $15.7 | Proposed | 2013-2013 | Proposed |
| 2013 Roads Projects, Red Deer County | Infrastructure | Red Deer County | Red Deer County | Innisfail-Sylvan Lake | Central | $15.6 | Proposed | 2013-2013 | Proposed |
| Road Improvements 34 St | Infrastructure | Strathcona County | Strathcona County | Sherwood Park | Capital | $15.6 | Proposed | 2013-2013 | Proposed |
| 'Blackfoot Point' Building 2 Office Building | Commercial / Retail | Blackfoot Business Park Inc. | Calgary | Calgary-Acadia | Calgary | $15.5 | Under Construction | 2013-2013 | Under construction. Centron Construction. |
| Fieldhouse (Recreation Facility) | Tourism / Recreation | Town of Blackfalds | Blackfalds | Lacombe-Ponoka | Central | $15.5 | Under Construction | 2012-2014 | Under construction. Manshield Construction. |
| New School (K to Grade 9), Gift Lake | Institutional | Alberta Education* | M.D. of Big Lakes | Lesser Slave Lake | Slave Lake | $15.5 | Announced | 2013-2014 | Announced. Marshall-Lee Construction Corp. |
| Saline Creek Supply Line, Water Treatment Plant | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $15.5 | Under Construction | 2010-2013 | Under construction. E Construction. |
| Pediatric Ambulatory Clinic Renovation | Institutional | Alberta Infrastructure | Edmonton | Edmonton-Riverview | Capital | $15.4 | Under Construction | 2012-2013 | Under construction. PCL Construction. |
| University of Alberta Endoscopy Relocation | Institutional | Alberta Infrastructure | Edmonton | Edmonton-Riverview | Capital | $15.4 | Under Construction | 2012-2013 | Under construction. PCL Construction Management. |
| 'RK East' Condominiums Phase 2 | Residential | Regency Developments | Edmonton | Edmonton-Highlands-Norwood | Capital | $15.3 | Under Construction | 2012-2013 | Under construction |
| New School (K to Grade 9) | Institutional | Alberta Education* | High Prairie | Lesser Slave Lake | Slave Lake | $15.3 | Proposed | 2013-2014 | Proposed. |
| Public Works Office and Shop Facility | Infrastructure | City of Spruce Grove | Spruce Grove | Spruce Grove-St. Albert | Capital | $15.3 | Nearing Completion | 2013-2013 | Nearing completion. CPI Construction Ltd. |
| RCMP Holding Cell and Traffic Operations Facility | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $15.3 | Nearing Completion | 2012-2013 | Nearing completion. Jen-Col Construction. |
| Chinook Station Project (LRT Project) | Infrastructure | City of Calgary | Calgary | Calgary-Acadia | Calgary | $15.0 | Nearing Completion | 2012-2013 | Nearing completion. PCL Construction Management. |
| Eco Station (Recycling Station), Northeast | Infrastructure | City of Edmonton | Edmonton | Edmonton-Beverly-Clareview | Capital | $15.0 | Proposed | Proposed | |
| Ethylene Storage Facility Cavern Development | Oil and Gas | Pembina Pipeline Corp. | Fort Saskatchewan | Athabasca-Sturgeon-Redwater | Capital | $15.0 | Announced | 2012-2013 | Announced |
| Highway 1 Crack Repair and Pave 12577 | Infrastructure | Alberta Transportation | M.D. of Bighorn No. 8 | Banff-Cochrane | Calgary | $15.0 | Proposed | Proposed. | |
| Holiday Inn Express and Suites Hotel | Tourism / Recreation | Tri Village Developments Ltd. | Spruce Grove | Spruce Grove-St. Albert | Capital | $15.0 | Announced | 2013-2014 | Announced |
| Lac Cardinal Supportive Housing | Institutional | Accredited Supportive Living Services Ltd. | Grimshaw | Dunvegan-Central Peace-Notley | Peace Country | $15.0 | Under Construction | 2012-2013 | Under construction. Jen - Col Construction. |
| New Facility, Whitemud Equine Centre | Tourism / Recreation | City of Edmonton / Whitemud Equine Learning Centre | Edmonton | Edmonton-Riverview | Capital | $15.0 | Proposed | Proposed. Two riding arenas, new barns, classrooms, multi - use areas. Pending funding. | |
| North Lethbridge Regional Park | Tourism / Recreation | City of Lethbridge | Lethbridge | Lethbridge-East | South Central | $15.0 | Proposed | 2014-2017 | Proposed, pending approvals. Estimated cost range $15M to $20M. |
| Power and Process Lab Upgrade / Expansion | Institutional | Lakeland College | Lloydminster | Vermilion-Lloydminster | Northeast | $15.0 | Proposed | Proposed for completion by mid - 2013. | |
| Sturgeon Medical Arts Centre | Commercial / Retail | NorthWest Property Corp. (NWPC) | St. Albert | Spruce Grove-St. Albert | Capital | $15.0 | Proposed | 2013-2013 | Proposed |
| Warehouse 2 Metis Tr/ Dwight McLellan Tr | Commercial / Retail | Morguard Investments Ltd. / Verus Partners Canada | Calgary | Calgary-McCall | Calgary | $15.0 | Nearing Completion | 2012-2013 | Nearing completion |
| North Highway Connector Contract A4 | Infrastructure | City of Red Deer | Red Deer | Red Deer-North | Central | $14.9 | Nearing Completion | 2012-2013 | Nearing completion. Pidherney's Trucking Ltd. |
| Apartment Building A | Residential | Cassel Developments Ltd. | Edmonton | Edmonton-Strathcona | Capital | $14.8 | Under Construction | 2012-2013 | Under construction |
| Lumino Building B Apartment Building | Residential | Kanas Corporation | Calgary | Calgary-Acadia | Calgary | $14.8 | Under Construction | 2011-2013 | Under construction |
| Edson and District Fieldhouse | Tourism / Recreation | Town of Edson | Edson | West Yellowhead | West Yellowhead | $14.5 | On Hold | On hold pending funding and municipal approval. Addition to existing Leisure Centre. | |
| Natural Swimming Pool, Borden Park | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Highlands-Norwood | Capital | $14.5 | Proposed | 2013-2014 | Proposed. Possible construction start summer 2013. |
| Septage Receiving Station | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $14.5 | Nearing Completion | 2012-2013 | Nearing completion. Graham Construction. |
| '1912Cross' Condo Project / SoBow | Residential | M2i Development Corp. | Calgary | Calgary-Fort | Calgary | $14.3 | Proposed | 2013-2014 | Proposed. ITC Construction Group. |
| Bonnybrook Wastewater Treatment Plant Upgrade | Infrastructure | City of Calgary | Calgary | Calgary-Fort | Calgary | $14.2 | Proposed | Proposed | |
| Interchange Highway 55 / SH813 and Bridge | Infrastructure | Alberta Transportation | Athabasca | Athabasca-Sturgeon-Redwater | North Central | $14.2 | Under Construction | 2011-2013 | Under construction. Carmacks Enterprises. |
| New Store, NE Edmonton | Commercial / Retail | Lowe's Companies Canada | Edmonton | Edmonton-Manning | Capital | $14.2 | Under Construction | 2012-2013 | Under construction. Norson Construction. |
| 'Britannia Crossing' Shopping Centre | Commercial / Retail | Opus Corp. | Calgary | Calgary-Elbow | Calgary | $14.1 | Under Construction | 2013-2014 | Under construction |
| 'Gala in Applewood' Apartment Building 'B' | Residential | The Redekop Group | Calgary | Calgary-Greenway | Calgary | $14.0 | Under Construction | 2012-2013 | Under construction |
| 'Westmount Square' Office Building | Commercial / Retail | OPTIMUS Building Corp. | Okotoks | Highwood | Calgary | $14.0 | Proposed | 2013-2014 | Proposed |
| Glenmore Water Treatment Plant Filter Gallery | Infrastructure | City of Calgary | Calgary | Calgary-Glenmore | Calgary | $14.0 | Announced | 2012 | Announced |
| Indoor Swimming Pool, Calling Lake | Tourism / Recreation | Hamlet of Calling Lake | M.D. of Opportunity No. 17 | Athabasca-Sturgeon-Redwater | Slave Lake | $14.0 | Proposed | Proposed. | |
| Modernization | Institutional | Alberta Education* | Cardston | Cardston-Taber-Warner | Southwest | $14.0 | Under Construction | 2012-2013 | Under construction. Cardston Elementary. Ward Bros. Construction. |
| Water and Sewer System, Marlboro | Infrastructure | Yellowhead County | Yellowhead County | West Yellowhead | West Yellowhead | $14.0 | Proposed | Proposed | |
| RCMP Detachment Building | Infrastructure | City of Lloydminster | Lloydminster | Vermilion-Lloydminster | Northeast | $13.9 | Under Construction | 2011-2013 | Under construction. Dowland Contracting. |
| CASA Centre Redevelopment | Institutional | CASA Services | Edmonton | Edmonton-Strathcona | Capital | $13.8 | Proposed | Proposed | |
| Modernization Phase 2 | Institutional | Alberta Education* | Edmonton | Edmonton-Strathcona | Capital | $13.7 | Proposed | 2012-2013 | Under construction. Strathcona HS and Forest Heights Elementary. Pentagon Structures and Theirman Construction. |
| Prairie Loop Blvd Contract 3 Phase 1 | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $13.7 | Announced | 2013-2014 | Announced. E Construction Ltd. Planned construction start April. |
| RCMP Detachment Expansion | Infrastructure | Strathcona County | Strathcona County | Strathcona-Sherwood Park | Capital | $13.7 | Proposed | 2013-2013 | Proposed |
| '634 Genco Court' Office Building | Commercial / Retail | Genco Development Corp. | Calgary | Calgary-Buffalo | Calgary | $13.6 | Proposed | 2013-2014 | Proposed. Planned construction start June 2013. |
| 'Encore at Kincora' Townhouse Complex | Residential | The Carlisle Group | Calgary | Calgary-Foothills | Calgary | $13.6 | Proposed | Proposed | |
| 2012 - 2013 Capital Roads Program | Infrastructure | Lac la Biche County | Lac La Biche County | Lac La Biche-St. Paul-Two Hills | Northeast | $13.6 | Under Construction | 2012-2013 | Under construction. Border Paving Ltd. Egg Lake Rd, Malbeuf Rd and Plamondon / Caslan Connector (Rge Rd 162). |
| Great Plains IV Industrial Park Building 2 | Commercial / Retail | Western Assets Management (WAM) | Calgary | Calgary-Fort | Calgary | $13.6 | Proposed | Proposed | |
| Northeast LRT Platform Extensions | Infrastructure | City of Calgary | Calgary | Calgary-Fort | Calgary | $13.6 | Proposed | 2012-2013 | Proposed. PCL Construction. Marlborough, Zoo, Bridgeland/Memorial, Rundle, Barlow/Max Bell and Franklin Stations. |
| New City Hall, Camrose | Infrastructure | City of Camrose | Camrose | Wetaskiwin-Camrose | Battle River | $13.4 | Announced | 2013-2014 | Announced. Bird Construction. Planned construction start April 2013. |
| Park Seville Building Conversion to Marriott Hotel | Tourism / Recreation | Marriott International / New Urban | Calgary | Calgary-Buffalo | Calgary | $13.4 | Announced | 2013-2014 | Announced |
| Stony Plain Road Streetscape | Infrastructure | City of Edmonton | Edmonton | Edmonton-Riverview | Capital | $13.4 | Announced | 2013-2013 | Announced. Carmacks Enterprises. Planned construction start March. |
| Civic Office Building (City Hall) / Library | Infrastructure | City of Fort Saskatchewan | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $13.3 | Under Construction | 2011-2013 | Under construction. Marshall - Lee Construction. |
| Boilermakers Training Facility | Institutional | Boilermakers Union 146 | Edmonton | Edmonton-Meadowlark | Capital | $13.2 | Under Construction | 2012-2013 | Under construction. Bird Construction. |
| Harvest Hills Office Park Building 'B' | Commercial / Retail | Qualico Commercial | Calgary | Calgary-Northern Hills | Calgary | $13.2 | Under Construction | 2012-2013 | Under construction |
| Highway 2 Pave (SH590) | Infrastructure | Alberta Transportation | Red Deer County | Innisfail-Sylvan Lake | Central | $13.2 | Announced | 2013-2014 | Announced. Carmacks Enterprises. |
| New Park Pavilions for Variety of Edmonton Parks | Tourism / Recreation | City of Edmonton | Edmonton | Edmonton-Highlands-Norwood | Capital | $13.2 | Proposed | 2013-2014 | Proposed. Tender for Borden Park closes April 9. |
| North Campus Redevelopment Phase 2B | Institutional | Bow Valley College | Calgary | Calgary-Fort | Calgary | $13.1 | Under Construction | 2012-2013 | Under construction. Stuart Olson Dominion Construction. |
| Stoney Industrial Centre Warehouse 5 | Commercial / Retail | WAM Development Group | Calgary | Calgary-Mackay-Nose Hill | Calgary | $13.1 | Under Construction | 2012-2013 | Under construction |
| Bonnylodge Seniors Facility Renovations | Institutional | Lakeland Lodge and Housing Foundation | Bonnyville | Bonnyville-Cold Lake | Northeast | $13.0 | Nearing Completion | 2012-2013 | Nearing completion. Gen-Mac ACL Inc. |
| Community Water System, Exshaw | Infrastructure | MD of Bighorn | M.D. of Bighorn No. 8 | Banff-Cochrane | Calgary | $13.0 | Proposed | Proposed | |
| Contract 10 Beale and Beaumount Crescent | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $13.0 | Proposed | 2013-2013 | Proposed |
| Copperstone Village' Residential Development | Residential | Copperstone Ltd. Partnership | Airdrie | Airdrie | Calgary | $13.0 | Under Construction | 2012-2013 | Under construction |
| Dufferin Intermodal Industrial Park | Infrastructure | City of Calgary | Calgary | Calgary-Fort | Calgary | $13.0 | Announced | Announced. | |
| New Costco Store | Commercial / Retail | Costco | St. Albert | St. Albert | Capital | $13.0 | Proposed | 2013-2013 | Proposed |
| New Spillway at Chain Lakes Prov Park | Infrastructure | Alberta Environment / Alberta Sustainable Resource Development | Nanton | Livingstone-Macleod | Southwest | $13.0 | Proposed | Proposed | |
| Northern Lights Regional Health Centre Renovations | Institutional | Alberta Infrastructure | Regional Municipality of Wood Buffalo | Fort McMurray-Wood Buffalo | Wood Buffalo | $13.0 | Under Construction | 2011-2014 | Under construction. Delnor Construction. |
| Racetrack and Entertainment Facilities, Balzac | Tourism / Recreation | United Horsemen of Alberta | Rocky View County | Chestermere-Rocky View | Calgary | $13.0 | Proposed | 2013-2014 | Proposed. Pending AGLC approval. |
| Wastewater Lagoon Upgrade | Infrastructure | Town of Didsbury | Didsbury | Olds-Didsbury-Three Hills | Central | $13.0 | Proposed | Proposed | |
| Water Treatment Plant Upgrades | Infrastructure | Barrhead Water Services Commission (County of Barrhead / Town of Barrhead) | Barrhead | Barrhead-Morinville-Westlock | North Central | $13.0 | Nearing Completion | 2012-2013 | Nearing completion. Westpro Infrastructure. |
| Marriott Town Place Suites Hotel | Tourism / Recreation | L - 7 Inc. | Red Deer | Red Deer-North | Central | $12.8 | Proposed | 2013-2013 | Proposed. |
| Brentwood Care Centre Addition | Institutional | Intercare Corp Group | Calgary | Calgary-Mountain View | Calgary | $12.6 | Under Construction | 2012-2013 | Under construction |
| Airport Sewer Servicing | Infrastructure | Regional Municipality of Wood Buffalo | Regional Municipality of Wood Buffalo | Fort McMurray-Conklin | Wood Buffalo | $12.5 | Completed | 2012-2013 | Completed. Graham Construction. |
| Regional Operations Centre | Pipelines | Access Pipeline | Fort Saskatchewan | Fort Saskatchewan-Vegreville | Capital | $12.5 | Announced | 2012-2013 | Announced |
| Replacement School (K to Grade 12) | Institutional | Alberta Education* | Two Hills | Lac La Biche-St. Paul-Two Hills | Northeast | $12.5 | Announced | 2013-2014 | Announced. Jen - Col Construction. |
| Redevelopment of Two Health Centres | Institutional | Alberta Infrastructure | Taber | Cardston-Taber-Warner | South Central | $12.4 | Proposed | Proposed | |
| Modernization Phase 3 (Fine Arts Area, Theatre, Gy | Institutional | Alberta Education* | Ponoka | Lacombe-Ponoka | Central | $12.1 | Proposed | Proposed. Ponoka Composite. | |
| 'Aspen Meadows' Buildings 5 and 6 | Residential | Landmark Urban Living | Edmonton | Edmonton-Mill Creek | Capital | $12.0 | Under Construction | 2012-2013 | Under construction |
| 'Drake' Apartment Building | Residential | Grosvenor Canada Ltd. | Calgary | Calgary-Buffalo | Calgary | $12.0 | Under Construction | 2011-2013 | Under construction |
| 'Pixel' Apartment Building | Residential | Battistella Developments | Calgary | Calgary-Mountain View | Calgary | $12.0 | Under Construction | 2012-2014 | Under construction |
| 'Spruce Ridge Estates' Apartment Building | Residential | Boardwalk Communities / Trico Homes | Calgary | Calgary-Currie | Calgary | $12.0 | Under Construction | 2012-2013 | Under construction |
| 2013 Arterial Road Maintenance (Potholes) | Infrastructure | City of Edmonton | Edmonton | Edmonton-Centre | Capital | $12.0 | Announced | 2013-2013 | Announced |
| Aquatic Centre |